History
  • No items yet
midpage
Marpac Construction Llc, V. Department Of Labor & Industries
82200-4
Wash. Ct. App.
Mar 28, 2022
Read the full case

Background

  • Marpac was general contractor on a West Seattle apartment project bordered by energized high-voltage lines; Seattle City Light had flagged only the east-side line.
  • Superintendent Todd Weeks never contacted the utility to confirm line voltages and assumed they were 26–50 kV.
  • Marpac continued work under the lines (including crane operations and a forklift with a boom attachment) despite subcontractor concerns.
  • On Sept. 26, 2016, crane rigging contacted the power lines during a lift; two workers suffered serious electrocution injuries.
  • DLI cited six violations (three serious, three serious-willful) and assessed $133,500; Marpac appealed only the three willful classifications.
  • The Board and King County Superior Court upheld the willful determinations; the Court of Appeals affirmed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
1) Whether failure to determine power-line voltage and use required encroachment precautions (WAC 296-155-53408(2)(b)) was willful Marpac: acted in good faith; used a 15-foot zone and believed Table 4 allowed a 10-foot clearance for ≤50 kV DLI: Marpac never confirmed voltage with the utility, could not rely on Option 3, and should have used more protective Option 2 (20 ft); continuing work showed indifference Affirmed willful — failure to confirm voltage and default to less protective measures showed plain indifference to safety
2) Whether operating crane/modified forklift under energized lines without deenergizing/grounding violated (WAC 296-155-53408(2)(d)(i)) willfully Marpac: did not realize attaching a boom made the forklift subject to crane rules and took steps to keep 10 ft clearance DLI: exceptions did not apply; ignorance and continued use of equipment capable of encroaching shows indifference Affirmed willful — operating the modified forklift under lines without required precautions supports willfulness
3) Whether failure to designate a qualified lift director (WAC 296-155-53401) was willful Marpac: Williams was assigned to perform lift director duties DLI: Williams denied being lift director, lacked training, and told supervisors he was not qualified Affirmed willful — either no lift director was appointed or an unqualified person was assigned, demonstrating indifference

Key Cases Cited

  • Shimmick Constr. Co., Inc. v. Dep't of Labor & Indus., 12 Wn. App. 2d 770 (2020) (standard of review for Board decisions; construing WISHA/agency deference)
  • Frank Coluccio Constr. Co. v. Dep't of Labor & Indus., 181 Wn. App. 25 (2014) (substantial evidence standard for agency findings)
  • Elder Demolition, Inc. v. Dep't of Labor & Indus., 149 Wn. App. 799 (2009) (willful violation defined as intentional disregard or plain indifference)
  • Brock v. Morello Bros. Constr., Inc., 809 F.2d 161 (1st Cir. 1987) (plain indifference test for willfulness)
  • Ga. Elec. Co. v. Marshall, 595 F.2d 309 (5th Cir. 1979) (employer ignorance of safety rules can support willful finding)
Read the full case

Case Details

Case Name: Marpac Construction Llc, V. Department Of Labor & Industries
Court Name: Court of Appeals of Washington
Date Published: Mar 28, 2022
Docket Number: 82200-4
Court Abbreviation: Wash. Ct. App.