History
  • No items yet
midpage
Mallory Fire Protection Servs. v. McShane Constr. Co.
A-16-752
Neb. Ct. App.
Oct 3, 2017
Read the full case

Background

  • McShane was general contractor for a 7‑building apartment project; Mallory contracted to design/install fire suppression for $345,000 (later $373,565 by change order).
  • Buildings 1–3 and 7 were NFPA‑13R (residential); Buildings 4–6 were NFPA‑13 (commercial), which required attic sprinklers or insulated interstitial spaces.
  • Dispute arose when Mallory’s bid included interstitial sprinklers for Bldgs 4–6 but the design plans omitted them; Mallory later installed some sprinklers then McShane chose to insulate interstitials instead.
  • Mallory left the job in March 2013 over alleged nonpayment; McShane retained Continental temporarily, then negotiated Mallory’s return with a March email agreement that McShane would pay $130,604.54 on final inspection for completion of Bldgs 4–6.
  • Mallory completed remedial work on Bldgs 4–6, then left permanently in May 2013 after McShane withheld further payment. McShane paid for various remedial expenses and sued; Mallory counterclaimed for unpaid work.
  • After a bench trial the district court found Mallory breached (walked off twice), awarded McShane $132,169.27 for certain remediation costs, and awarded Mallory $130,604.54 for partial performance; both parties appealed.

Issues

Issue Plaintiff's Argument (McShane) Defendant's Argument (Mallory) Held
Contract construction / March emails: whether emails modified or waived contract rights Emails did not modify/waive the contract; waiver requires clear act; court should enforce original terms Emails were a clarification enforceable to pay agreed amount upon completion Court: emails were a clarification of duties (not waiver); treating them as clarification did not prejudice McShane; affirmed
Breach & substantial performance / divisibility: whether contract divisible and Mallory substantially performed Contract not divisible; Mallory breached and should not recover for unfinished work Contract divisible by building; Mallory substantially performed on Bldgs 1–6 and is entitled to fair value Court: contract was not divisible as written but Mallory conferred substantial benefit; Mallory entitled to recovery ($130,604.54) for partial performance; result affirmed though reasoning differs
Proof of damages to McShane: whether McShane proved its claimed remediation and consequential losses with reasonable certainty McShane proved various categories (insulation, drywall, labor, etc.) and other consequential losses Many claimed items were speculative, undocumented, or remote; burden was on McShane to prove amounts Court: awarded $132,169.27 for specific proven items (insulation, drywall, painting, cleaning, temp labor); rejected other categories for lack of certainty or proof; award affirmed
Prejudgment interest & change order/other Mallory claims: whether Mallory entitled to additional recovery (change order, Bldg 7, prejudgment interest) Mallory sought amounts under change order, completion of Bldg 7, and prejudgment interest Mallory lacked proof of reasonable fair value beyond the email amount; dispute over liquidated claim precluded prejudgment interest Court: refused additional change‑order and Bldg‑7 recovery for lack of proof; prejudgment interest denied because claim was not liquidated/controverted; affirmed
Negligence claims: whether tort claims survive despite contract remedy McShane asserted independent tort duties were breached by Mallory Mallory argued contractual remedies control; tort theories duplicative Court: dismissed negligence claims as alternative contract theories; even if error, harmless because damages overlap and proof insufficient; affirmed

Key Cases Cited

  • Labenz v. Labenz, 291 Neb. 455 (contract construction standard)
  • D & S Realty v. Markel Ins. Co., 280 Neb. 567 (waiver principles)
  • Selig v. Wunderlich Contracting Co., 160 Neb. 215 (modification requires consideration)
  • Anderson Excavating v. SID No. 177, 265 Neb. 61 (bench‑trial factual findings not reversed unless clearly wrong)
  • Henderson v. City of Columbus, 285 Neb. 482 (credibility and factfinding in bench trials)
  • Gibbons Ranches v. Bailey, 289 Neb. 949 (contract ambiguity rule)
  • RN Campbell Indus. v. Midwest Renewable Energy, 294 Neb. 326 (substantial performance and recovery)
  • Latzel v. Bartek, 288 Neb. 1 (affirming correct result on different reasoning)
  • BSB Constr. v. Pinnacle Bank, 278 Neb. 1027 (prejudgment interest analysis)
  • Brook Valley Ltd. Part. v. Mutual of Omaha Bank, 285 Neb. 157 (reasonable controversy for interest)
  • Roskop Dairy v. GEA Farm Tech., 292 Neb. 148 (prejudgment interest recoverable only as provided by statute)
  • Archbold v. Reifenrath, 274 Neb. 894 (liquidated claim two‑pronged inquiry for prejudgment interest)
  • Donut Holdings v. Risberg, 294 Neb. 861 (bench‑trial findings have effect of jury verdict)
Read the full case

Case Details

Case Name: Mallory Fire Protection Servs. v. McShane Constr. Co.
Court Name: Nebraska Court of Appeals
Date Published: Oct 3, 2017
Docket Number: A-16-752
Court Abbreviation: Neb. Ct. App.