History
  • No items yet
midpage
Mako Investments v. West Coast Contractors of Nevada CA3
C073867
| Cal. Ct. App. | Oct 3, 2016
Read the full case

Background

  • West Coast was the general contractor on a $2.6M Lake Tahoe erosion/stream-restoration public works project; Zephyr (subcontractor) performed earthwork and later assigned claims to Mako (creditor/assignee). Fidelity issued West Coast’s payment bond.
  • Dispute: West Coast withheld progress payments to Zephyr, then terminated and sought to substitute another subcontractor. County mailed a statutorily required substitution notice to Zephyr’s last known address by certified mail, but Zephyr did not receive it and did not file objections.
  • Trial jury awarded Mako/Zephyr $915,045 in compensatory and $638,422 in punitive damages (total $1,553,467); jury also resolved cross-complaint claims favorably to Zephyr.
  • Trial court granted judgment notwithstanding the verdict (JNOV) in part, reducing compensatory damages to $220,045, vacating punitive damages, denying some claims, and awarding prejudgment interest only on certain amounts; it also awarded Mako/Zephyr reduced attorney fees (35% of requested) and costs.
  • Mako/Zephyr appealed the JNOV reductions, punitive-damage vacatur, fee/cost reductions, and interest rulings; West Coast cross-appealed a licensing-related jury instruction. Court of Appeal affirmed.

Issues

Issue Plaintiff's Argument (Mako/Zephyr) Defendant's Argument (West Coast) Held
Whether statutory substitution under Pub. Contract Code §4107 requires actual receipt of the County’s certified/registered-mail notice (due process challenge) §4107 should require actual notice or reasonable diligence; lack of actual receipt deprived Zephyr of substantive rights and due process Compliance with the statute (mailing to last known address by certified/registered mail) is sufficient; failure to receive notice is the subcontractor’s problem and the administrative process is binding Mailing to last known address satisfied §4107; Zephyr’s failure to receive or object meant consent by operation of statute; administrative finding preclusive absent timely review
Whether punitive damages were legally available Jury found malice/ oppression based on withholding payments, secret plan to terminate, and other conduct; these support punitive damages Substitution was lawful and many jury findings arise from contract-related conduct; punitive damages are not allowed for contract breaches or where statutory penalties exist (double punishment) Vacated punitive damages: conduct supporting them was contract-related and/or remedied by statutory penalties (prompt-payment interest), so punitive damages were not legally recoverable
Prejudgment interest on lost profits and on materials/equipment left on site Lost profits and $15,000 for materials were liquidated or calculable and thus entitled to prejudgment interest from date of loss Amounts were unliquidated or not sufficiently ascertainable; lost profits not recoverable after JNOV Denied prejudgment interest on lost profits (court also refused to award lost profits); denied interest on $15,000 because valuation evidence was sketchy/unliquidated
Reasonableness and apportionment of attorney fees and costs Fees are largely tied to a common core of facts; claims were intertwined so full requested fees are recoverable; hourly rates supported by declarations Plaintiff overlitigated many unsuccessful tort claims; billing contained excessive, duplicative, or vague entries; award should be reduced to reflect limited success Trial court did not abuse discretion: reduced fees to 35% of requested based on limited success, overlitigation, excess hours, and local reasonable rates; costs reduction likewise upheld
Cross-appeal: whether jury instruction on contractor-license disassociation (B&P §7068.2/7083) was erroneous (West Coast) jury instruction omitted automatic 90-day suspension and thus misstated the law, warranting reversal Trial court’s instruction followed statutory scheme and later amendments; instruction was correct and nonprejudicial Instruction upheld: court’s reading of §7068.2 and related provisions is correct and deletion of retroactive-suspension language means the instruction given was proper

Key Cases Cited

  • Southern Cal. Acoustics Co. v. C. V. Holder, Inc., 71 Cal.2d 719 (Cal. 1969) (listed subcontractor has a statutory right to perform unless substitution is authorized by statute; wrongful substitution supports a private action)
  • Affholder, Inc. v. Mitchell Engineering, Inc., 153 Cal.App.4th 510 (Cal. Ct. App. 2007) (administrative substitution process under §4107 is binding if not timely challenged; plaintiff must exhaust administrative remedies)
  • Interior Systems, Inc. v. Del E. Webb Corp., 121 Cal.App.3d 312 (Cal. Ct. App. 1981) (legislative procedure in §4107 intended to produce binding results unless set aside by court review; administrative determinations conclusive when not attacked)
  • Titan Electric Corp. v. Los Angeles Unified School Dist., 160 Cal.App.4th 188 (Cal. Ct. App. 2008) (substantial compliance with §4107 procedural objectives can validate a post hoc substitution; absence of bid-shopping evidence supports validity)
  • Cates Construction, Inc. v. Talbot Partners, 21 Cal.4th 28 (Cal. 1999) (punitive damages are unavailable for mere breach of contract unless an independent tort duty is breached)
Read the full case

Case Details

Case Name: Mako Investments v. West Coast Contractors of Nevada CA3
Court Name: California Court of Appeal
Date Published: Oct 3, 2016
Docket Number: C073867
Court Abbreviation: Cal. Ct. App.