History
  • No items yet
midpage
M & M Electrical Contractor, Inc. v. Cumberland Electric Membership Corporation
529 S.W.3d 413
Tenn. Ct. App.
2016
Read the full case

Background

  • Cumberland EMC contracted with M&M (three-year construction contract) to perform energized line work using four five-person crews; Cumberland required trucks to be grounded during "hot work."
  • On April 16, 2014 at a complex, highly energized New Shackle Island job, six M&M bucket trucks were observed ungrounded; M&M owners admitted knowledge of Cumberland’s grounding policy but disputed some facts.
  • Cumberland safety staff investigated, and on Good Friday (April 18) Cumberland’s safety coordinator told M&M’s co-owner Julia Miller that all M&M trucks must be equipped with and use grounds by Monday, April 21.
  • On April 21 Cumberland engineers inspected multiple M&M jobs and observed (or reasonably inferred) two crews performing or having just performed energized work with ungrounded trucks; M&M foremen disputed parts of the account.
  • Cumberland’s board authorized termination; Cumberland terminated M&M for safety violations and paid for completed work. M&M sued for breach of contract and bad faith; the chancery court found a material breach and justified termination. M&M appealed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether evidence supports finding M&M performed ungrounded hot work on April 21 M&M (through foremen) denied performing hot work; claimed buckets were raised only to drain water Cumberland relied on engineer Abernathy’s observations and reasonable inferences that hot work had been performed Court credited Cumberland’s witnesses; evidence did not preponderate against trial court finding of ungrounded energized work
Whether breach (ungrounded trucks) was material M&M: isolated incidents, long period without injury, breach not substantial enough to justify termination Cumberland: safety violations risk death/injury; safety provisions in contract and express termination-for-safety clause Court held breach was material given severity and safety-focused contract terms; termination justified
Whether Cumberland had to give written notice and 20-day cure period under contract M&M: contract required written notice and opportunity to cure; implied covenant of good faith required notice Cumberland: contract provisions allowed owner to act without prior written notice; common-law remedies and right to terminate for material breach remain Court held contract did not mandate written notice here; even if notice rule applied, Cumberland gave adequate notice and opportunity; termination in good faith
Whether termination breached implied covenant of good faith and fair dealing M&M: Cumberland terminated abruptly without adequate notice/cure opportunity Cumberland: acted reasonably, safety required prompt action, and it had contractual and common-law rights Court held Cumberland acted within its rights and in good faith; no damages for breach of implied covenant

Key Cases Cited

  • DePasquale v. Chamberlain, 282 S.W.3d 47 (Tenn. Ct. App. 2008) (materiality required to relieve non‑breaching party)
  • Forrest Constr. Co. v. Laughlin, 337 S.W.3d 211 (Tenn. Ct. App. 2009) (factors for material breach analysis)
  • State v. McCormick, 494 S.W.3d 673 (Tenn. 2016) (deference to trial court credibility findings)
  • Hughes v. Metro. Gov’t of Nashville & Davidson Cnty., 340 S.W.3d 352 (Tenn. 2011) (deference where trial judge observed witnesses)
  • McClain v. Kimbrough Constr. Co., 806 S.W.2d 194 (Tenn. Ct. App. 1990) (construction context: notice and reasonable opportunity to perform/cure)
  • Dick Broad. Co. of Tenn. v. Oak Ridge FM, Inc., 395 S.W.3d 653 (Tenn. 2013) (recognition of implied covenant of good faith and limits tied to contractual expectations)
  • Wallace v. Nat’l Bank of Commerce, 938 S.W.2d 684 (Tenn. 1996) (scope of implied duty of good faith depends on contract)
  • Houston Bros. v. Dickson Planing Mill Co., 15 S.W.2d 749 (Tenn. 1929) (immediate demand appropriate when no time required to perform next step)
Read the full case

Case Details

Case Name: M & M Electrical Contractor, Inc. v. Cumberland Electric Membership Corporation
Court Name: Court of Appeals of Tennessee
Date Published: Nov 4, 2016
Citation: 529 S.W.3d 413
Docket Number: M2016-00358-COA-R3-CV
Court Abbreviation: Tenn. Ct. App.