History
  • No items yet
midpage
502 F. App'x 934
Fed. Cir.
2013
Read the full case

Background

  • M.E.S., Inc. appeals the Armed Services Board of Contract Appeals’ denial of two equitable-adjustment claims on a Corps contract.
  • The Corps awarded a $10.3 million firm-fixed-price contract to design and build a fitness center at McGuire AFB, with a 720-day schedule and a planned completion date of Nov. 4, 2003.
  • Project delays occurred due to severe weather and asbestos discovery; the Corps extended the completion date 12 times by 345 days and paid $626,469 in additional compensation.
  • Most modifications were bilateral and reserved M.E.S.’s right to request delay/impact compensation and overhead adjustments; at least one modification included home office overhead.
  • Construction was substantially completed on Oct. 14, 2004; M.E.S. submitted five equitable-adjustment claims totaling $1,593,949, which the contracting officer denied; the Board sustained two claims and denied three, including the two on appeal.
  • The agency’s Board findings and the evidentiary record are the basis for this court’s review under 28 U.S.C. § 1295(a)(10).

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether government delays/inefficiencies caused cost overruns. M.E.S. argues delays caused overruns through inefficiencies and cost inflation. Board found no persuasive evidence linking delays to the increased costs. Board’s finding is supported by substantial evidence.
Whether government-directed acceleration existed. M.E.S. contends delays entitled it to extended time; government forced earlier completion. No extension beyond Oct. 14, 2004; no acceleration proven. No entitlement to additional time or acceleration shown.
Whether M.E.S. is entitled to additional home office overhead (Eichleay). Claims rely on Eichleay/overhead calculation for delays. Standby/evidence requirements not met; calculation deficient and not substantiated. Substantial evidence supports denial of Eichleay/overhead damages.

Key Cases Cited

  • Wilner v. United States, 24 F.3d 1397 (Fed. Cir. 1994) (contractor must prove liability and damages for delays)
  • Fraser Constr. Co. v. United States, 384 F.3d 1354 (Fed. Cir. 2004) (constructive acceleration requires government-imposed deadline shorter than entitlement)
  • Interstate General Gov’t Contractors, Inc. v. West, 12 F.3d 1053 (Fed. Cir. 1993) (standby/interruptions required for Eichleay analysis)
  • Cmty. Heating & Plumbing Co. v. Kelso, 987 F.2d 1575 (Fed. Cir. 1993) (standby and interruption requirements for Eichleay damages)
  • C.B.C. Enters., Inc. v. United States, 978 F.2d 669 (Fed. Cir. 1992) (home office overhead calculations in contract disputes)
Read the full case

Case Details

Case Name: M.E.S., Inc. v. McHugh
Court Name: Court of Appeals for the Federal Circuit
Date Published: Jan 15, 2013
Citations: 502 F. App'x 934; 2012-1457, 2012-1466
Docket Number: 2012-1457, 2012-1466
Court Abbreviation: Fed. Cir.
Log In