28 F.4th 1285
D.C. Cir.2022Background
- LSP Transmission Holdings II, LLC (a transmission developer) challenged FERC’s termination of a §206 investigation into ISO New England’s implementation of Order No. 1000 competitive-selection rules.
- Order No. 1000 eliminated federal rights of first refusal for transmission projects and directed competitive selection, but allowed an exception for reliability projects when solicitation would delay urgently needed work.
- FERC’s Compliance Order allowed ISO New England to treat projects as "immediate need" if the reliability need arises within three years (using a need-by date), not ISO-NE’s proposed five-year window.
- ISO New England routinely used conservative need-by dates that often preceded projects’ expected in-service dates; ISO-NE exempted nearly all recent reliability projects from competitive solicitation.
- FERC issued a Show Cause Order under FPA §206, invited interventions (including LSP), and ultimately concluded in a Termination Order that ISO-NE’s use of need-by dates and application of the exemption were just and reasonable.
- LSP petitioned for review in the D.C. Circuit, arguing lack of competition because FERC/ISO-NE’s use of need-by dates improperly swallows the competition requirement; the court denied the petition.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Standing | LSP was ready, willing, and able to bid and was deprived of opportunities by ISO‑NE’s implementation, so it suffered Article III injury | FERC argued no change to planning criteria, so LSP suffered no concrete injury | Court: LSP has standing; it identified specific projects and lost opportunity to compete |
| Reviewability (Heckler immunity) | FERC’s Show Cause/Termination Order is a substantive adjudicative decision subject to judicial review | FERC claimed its action was an enforcement/declination decision immune from review under Heckler v. Chaney | Court: Order was a reviewable §206 contested proceeding and decided on the merits; not immune |
| Use of need-by dates vs. in-service dates | LSP: Commission should require in-service dates for the three-year exemption threshold because need-by dates let nearly all projects bypass competition | FERC: Using need-by dates is reasonable to ensure reliability and avoid delaying urgent projects; consistent with precedent and NERC standards | Court: Upheld FERC’s use of need-by dates as reasonable and adequately explained |
| Alleged departure from Order No. 1000 / exception overuse | LSP: The frequency of exemptions shows the exception swallows the rule and departs from Order No.1000 | FERC: Frequency alone is insufficient; ISO‑NE applied the established criteria correctly; policy balancing is for the agency | Court: Deferred to FERC’s policy judgment and found no unlawful departure; petition denied |
Key Cases Cited
- O’Donnell Constr. Co. v. District of Columbia, 963 F.2d 420 (D.C. Cir. 1992) (standing standard where denial of opportunity to compete injures bidder)
- Carney v. Adams, 141 S. Ct. 493 (2020) (Article III standing principles)
- Ne. Fla. Chapter of Associated Gen. Contractors v. City of Jacksonville, 508 U.S. 656 (1993) (standing requires readiness and ability to perform)
- Heckler v. Chaney, 470 U.S. 821 (1985) (agency enforcement declinations and reviewability doctrine)
- Pub. Citizen, Inc. v. FERC, 7 F.4th 1177 (D.C. Cir. 2021) (FPA §206 proceedings produce substantive adjudicative decisions)
- Citizens to Pres. Overton Park, Inc. v. Volpe, 401 U.S. 402 (1971) (agency action reviewability and scope of judicial review)
- Bechtel v. FCC, 10 F.3d 875 (D.C. Cir. 1993) (agency may rely on prior decisions when earlier reasoning remains valid)
- Fresno Mobile Radio, Inc. v. FCC, 165 F.3d 965 (D.C. Cir. 1999) (courts defer to agency policy judgments in balancing competing regulatory goals)
