Lsf Structures Ltd & Lightweight Steel Framing 2007 Ltd, Apps v. Brix Condos, Resps
73427-0
| Wash. Ct. App. | Nov 7, 2016Background
- Brix Condominium LLC (developer) and W.G. Clark CM Inc. (original GC, later assigned to Brix) had a subcontract with LSF Structures Ltd./Lightweight Steel Framing 2007 Ltd. that required nonbinding mediation followed by binding arbitration for disputes.
- Section U3 required the subcontractor to submit a "full claim in writing" with "detailed cost documentation" and "all points of argument" to the GC president, and to wait 30 days before filing any mediation, arbitration, or litigation.
- WGC assigned its interest to Brix (July 2008); LSF was terminated the same month and a dispute over unpaid invoices followed. Brix demanded arbitration in February 2009 and the parties selected a mediator/arbitrator but did not set dates.
- LSF filed a court complaint in August 2009 (later dismissed without prejudice), and again filed a complaint based on the same facts in July 2014, seeking breach of contract, quantum meruit, and recovery of a contractor registration bond and requesting a stay pending arbitration.
- Brix moved for summary judgment arguing LSF never satisfied the Section U3 condition precedent before suing; LSF relied on a conclusory declaration and a one-page summary of amounts claimed. The trial court granted summary judgment and dismissed with prejudice; this appeal followed.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether LSF's lawsuit should be treated as a complaint to compel arbitration | LSF said it filed the suit to compel arbitration and that an arbitrator should decide whether the condition precedent was met | Brix said the complaint sought damages and was not a petition to compel arbitration, so the court could decide compliance with the condition precedent | Held: The complaint was not a petition to compel arbitration; the trial court properly addressed whether LSF complied with Section U3 |
| Whether LSF satisfied the subcontract's express condition precedent (Section U3) before suing | LSF asserted substantial compliance via Malcolm's declaration and dealings/communications with Brix and Andersen | Brix showed absence of documentary proof of a "full claim in writing," detailed cost documentation, or all points of argument as required | Held: LSF failed to raise a genuine issue of material fact; its evidence was conclusory and insufficient under CR 56(e) |
| Whether substantial compliance (vs. strict compliance) applies to the condition precedent here | LSF relied on Staples to argue substantial compliance suffices | Brix argued Staples was limited to insurer/insured quasi‑fiduciary contexts and does not apply | Held: Staples is inapplicable; no fiduciary duty here, so LSF could not rely on that relaxed standard |
| Whether Brix waived the condition precedent by demanding arbitration or whether dismissal with prejudice was improper without showing prejudice | LSF argued waiver because Brix demanded arbitration and that dismissal should require prejudice | Brix argued Section U3 applies to any claim type (mediation, arbitration, litigation), so its demand did not waive the condition; prejudice standard arose only in special insurer/insured cases | Held: No waiver; dismissal with prejudice was proper given LSF filed on the statute of limitations deadline and failed to satisfy the condition precedent |
Key Cases Cited
- Eicon Construction, Inc. v. Eastern Washington University, 174 Wn.2d 157 (summary judgment standard and CR 56 principles)
- Walter Implement, Inc. v. Focht, 107 Wn.2d 553 (party seeking contract enforcement bears burden to prove performance of condition precedent)
- Ross v. Harding, 64 Wn.2d 231 (failure to satisfy material condition precedent relieves defendant of liability)
- Staples v. Allstate Ins. Co., 176 Wn.2d 404 (application of substantial compliance in insurer/insured context)
- Young v. Key Pharmaceuticals, Inc., 112 Wn.2d 216 (plaintiff must make factual showing of essential elements; conclusory statements insufficient)
