midpage
Projects
Sign in to see your projects.
20 F.4th 1
D.C. Cir.
2021
Read the full case

Background:

  • Six Entergy utilities operated under a System Agreement requiring coordinated planning and roughly equalized production costs; Section 30.03 governed allocation to native load, Section 30.04 governed opportunity (off-system) sales, and Section 4.05 governed Joint Account Sales.
  • In 2009 Louisiana PSC sued, alleging Entergy Arkansas made off-system sales of low-cost energy to third parties while improperly treating them as native load under Section 30.03.
  • Phase 1: FERC found Entergy Arkansas could make opportunity sales but had violated the System Agreement by accounting some third-party sales as native load; FERC ordered refunds to other system utilities and set a methodology for damages to be worked out in later phases.
  • During Phase 3 Entergy Arkansas identified a subset (the Grand Gulf Sales, Jan–Sept 2000) that it said were accounted for as Joint Account Sales under Section 4.05 and thus should be excluded from the damage calculation; the ALJ rejected exclusion but FERC reversed and excluded the Grand Gulf Sales as outside the Section 30.03 remedy.
  • FERC held that whether the Grand Gulf Sales were properly accounted for under Section 4.05 was beyond the scope of the Phase 3 proceeding and that Louisiana could file a separate complaint.
  • Louisiana filed a 2019 complaint challenging the Grand Gulf accounting; FERC dismissed it as barred by a 2015 Settlement Agreement in which settling parties waived claims arising from the System Agreement that were not filed and served before the settlement. Louisiana petitioned for review; the D.C. Circuit denied the petitions.

Issues:

Issue Plaintiff's Argument Defendant's Argument Held
Whether excluding the Grand Gulf Sales was an arbitrary change in FERC position FERC previously grouped disputed sales ("Opportunity Sales") to include Grand Gulf, so excluding them is a reversal requiring reasoned explanation FERC never previously decided that Grand Gulf were violations; the defined term only identified the set of disputed sales, not a finding on each sale No arbitrary change: FERC had not taken a prior position on Grand Gulf and provided a rational explanation for exclusion
Whether FERC’s factual finding that Grand Gulf Sales were accounted as Joint Account Sales is supported by substantial evidence Louisiana: FERC cited no evidence that Entergy always classified Grand Gulf as Joint Account Sales FERC: record includes Louisiana’s own witness conceding Grand Gulf were treated as Joint Account Sales; substantial evidence standard is low Held supported: record evidence met the substantial-evidence standard
Whether FERC should have remedied Grand Gulf Sales in the same Phase 3 proceeding Louisiana: Grand Gulf caused similar harm and should have been remedied here FERC: Phase 3 targeted Section 30.03 violations; Grand Gulf implicated Section 4.05 and a separate accounting dispute outside the remedy scope Held: FERC reasonably exercised discretion to treat the issues separately
Whether the 2019 Complaint was barred by the 2015 Settlement Agreement (waiver, estoppel, mutual mistake) Louisiana: 2019 claims were preserved by the 2009 complaint and by Section G(2)’s savings clause; alternatively, estoppel or mutual mistake prevents barring the claim Entergy/FERC: 2019 complaint alleges different legal theory (accounting under Section 4.05); G(1) waiver bars unfiled claims, G(2) is limited to bandwidth/cost-allocation disputes; estoppel/mutual mistake not shown Held: FERC reasonably interpreted and enforced the Settlement Agreement; 2019 Complaint barred; estoppel and mutual mistake claims fail

Key Cases Cited

  • Motor Vehicle Mfrs. Ass'n of U.S., Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (1983) (agency action must be reasoned and not arbitrary)
  • Vermont Yankee Nuclear Power Corp. v. Natural Res. Def. Council, 435 U.S. 519 (1978) (agencies have procedural discretion in agency rulemaking and adjudication)
  • Mobil Oil Expl. & Producing Se. Inc. v. United Distrib. Cos., 498 U.S. 211 (1991) (agency discretion to handle related but discrete issues)
  • Consolidated Edison Co. v. NLRB, 305 U.S. 197 (1938) (definition of substantial evidence)
  • New Hampshire v. Maine, 532 U.S. 742 (2001) (judicial estoppel standard)
  • ATC Petroleum, Inc. v. Sanders, 860 F.2d 1104 (D.C. Cir. 1988) (elements of equitable estoppel)
  • Harbor Ins. Co. v. Stokes, 45 F.3d 499 (D.C. Cir. 1995) (mutual mistake rescission standard)
  • Bituminous Coal Operators' Ass'n v. Connors, 867 F.2d 625 (D.C. Cir. 1989) (mutual mistake doctrine)
  • FPL Energy Main Hydro LLC v. FERC, 287 F.3d 1151 (D.C. Cir. 2002) (standard for substantial evidence review in FERC cases)
  • Louisiana Pub. Serv. Comm'n v. FERC, 522 F.3d 378 (D.C. Cir. 2008) (background on System Agreement and remedies)
  • Louisiana Pub. Serv. Comm'n v. FERC, 482 F.3d 510 (D.C. Cir. 2007) (standard of review for FERC orders)
  • Louisiana Pub. Serv. Comm'n v. FERC, 866 F.3d 426 (D.C. Cir. 2017) (interpretation of System Agreement cost-equalization remedies)
Read the full case

Case Details

Case Name: Louisiana Public Service Commission v. FERC
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Dec 7, 2021
Citations: 20 F.4th 1; 20-1104
Docket Number: 20-1104
Court Abbreviation: D.C. Cir.
Log In
    Louisiana Public Service Commission v. FERC, 20 F.4th 1