History
  • No items yet
midpage
866 F.3d 426
D.C. Cir.
2017
Read the full case

Background

  • Entergy operated five utility companies under a System Agreement allocating production costs; FERC concluded the allocations were unjust and adopted a "Bandwidth Remedy" to keep each company within ±11% of system average production costs.
  • FERC's Opinion No. 480 (June 1, 2005) announced the Remedy and stated it would be "effective" January 1, 2006, with Bandwidth Payments to be calculated after each calendar year once Form 1 data were filed.
  • This Court (LPSC v. FERC) upheld the Bandwidth Remedy but remanded because FERC had not adequately explained delaying the Remedy’s effective date beyond June 1, 2005.
  • On remand FERC advanced the effective date to June 1, 2005 and applied the Remedy to June–December 2005; Payments based on 2006 and 2007 data were already exchanged in 2007 and 2008 respectively.
  • Louisiana Public Service Commission (LPSC) challenged FERC’s remand implementation, arguing (1) a remaining 17‑month gap (Jan 2006–May 2007) left unremedied, and (2) FERC engaged in unlawful retroactive ratemaking by using the post‑2006 formula for the 2005 period rather than the June 2005 methodology.
  • The D.C. Circuit found FERC suitably explained advancing the effective date, concluded all disparities from June 1, 2005 onward were remedied through Payments, and rejected LPSC’s retroactive‑ratemaking challenge; the petition was denied except the court remanded the separate Section 206 refunds issue for further consideration.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether FERC left an unremedied gap (Jan 2006–May 2007) after advancing the Remedy to June 1, 2005 LPSC: Remedy is only "effective" when Payments are exchanged, so delayed Payments meant a two‑year delay needing cure FERC: "Effective date" can mean the period from which disparities are measured; Payments occur after year‑end data; payments for 2006/2007 already cured disparities Held: FERC reasonably construed and implemented the Remedy; no unresolved gap post‑June 1, 2005
Whether FERC’s remand application to June–Dec 2005 constituted unlawful retroactive ratemaking by using a later (2006) formula instead of the June 2005 methodology LPSC: FERC should have applied the methodology announced in June 2005 to the 2005 period FERC: The 2006 methodology adhered to the 2005 formulation; FERC had authority to remedy errors after remand; parties waived some challenges earlier Held: No unlawful retroactive ratemaking; LPSC waived prior challenge; FERC acted within its remedial authority
Proper scope of judicial review of FERC’s remedial design and rate implementation LPSC: Agency must fix payments timing to make rates "in force" without delay FERC: Courts owe deference to agency remedy design and rate‑making methods where explained Held: Court applied arbitrary-and-capricious standard and deferred to FERC’s reasonable explanations
Whether remand should also address Section 206 refunds for an earlier period (Sept 2001–May 2003) LPSC: Sought relief on that refunds period as well FERC/Court: Recent precedent requires reconsideration of that refunds denial Held: Court remanded the Section 206 refunds denial to FERC for further consideration

Key Cases Cited

  • Louisiana Pub. Serv. Comm’n v. FERC, 522 F.3d 378 (D.C. Cir.) (upholding Bandwidth Remedy; remand for explanation of delayed effective date)
  • Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (1983) (arbitrary-and-capricious standard for agency action)
  • FERC v. Elec. Power Supply Ass’n, 136 S. Ct. 760 (2016) (deference to FERC in rate design and remedial choices)
  • Morgan Stanley Capital Grp. Inc. v. Pub. Util. Dist. No. 1, 554 U.S. 527 (2008) (deference in utility rate determinations)
  • Niagara Mohawk Power Corp. v. FPC, 379 F.2d 153 (D.C. Cir. 1967) (agency discretion in crafting remedies)
  • Pub. Utils. Comm’n v. FERC, 988 F.2d 154 (D.C. Cir. 1993) (FERC authority to remedy errors after court reversal)
  • Xcel Energy Servs. v. FERC, 815 F.3d 947 (D.C. Cir. 2016) (standards on retroactive ratemaking and FERC remedial power)
  • City of Anaheim v. FERC, 558 F.3d 521 (D.C. Cir. 2009) (distinguishing retroactive surcharges imposed not in response to court reversal)
Read the full case

Case Details

Case Name: Louisiana Public Service Commission v. Federal Energy Regulatory Commission
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Aug 8, 2017
Citations: 866 F.3d 426; 14-1063
Docket Number: 14-1063
Court Abbreviation: D.C. Cir.
Log In
    Louisiana Public Service Commission v. Federal Energy Regulatory Commission, 866 F.3d 426