History
  • No items yet
midpage
343 So.3d 831
La. Ct. App.
2022
Read the full case

Background

  • Lonesome Development and the Town of Abita Springs executed a Development Agreement (PUD Agreement) in January 2018 under Louisiana’s Development Agreement Law (LDAL) to develop the 168-acre “Abita Meadows” PUD; the Board of Aldermen approved the preliminary plat.
  • After municipal engineers approved infrastructure plans, Mayor Lemons authorized construction to proceed in May 2018; Lonesome cleared the site and installed ponds, utilities, roads and other infrastructure and invested over $6 million.
  • In July 2019 the town’s attorney sent a letter asserting ordinance violations (including failure to submit a final plat within one year and tree‑removal violations) and declaring the PUD null and void; town officials then stopped inspections and work.
  • Lonesome sued in August 2019 for breach, specific performance, injunctive relief, and damages; Abita Springs asserted the PUD had been terminated and raised procedural exceptions.
  • On June 3, 2021 (amended April 5, 2022), the trial court held Abita Springs substantially breached the PUD Agreement, ordered specific performance and an injunction, and awarded Lonesome $4.9 million plus attorney’s fees and costs; Abita Springs appealed.

Issues

Issue Plaintiff's Argument (Lonesome) Defendant's Argument (Abita Springs) Held
Can the municipality unilaterally terminate the PUD Agreement under LDAL §4780.23 and render the court without jurisdiction? Termination under §4780.23 requires substantial evidence and is subject to judicial review; Lonesome sued to enforce the agreement. §4780.23 permits municipal termination after periodic review; Ordinance 519 validly terminated the PUD so the court lacks jurisdiction. Court: Municipality cannot unilaterally terminate by ordinance without proving noncompliance; trial court properly retained jurisdiction and denied exceptions.
Which controls timing for final plat submission: local ordinance (one‑year rule) or the PUD Agreement/Flow Chart? The PUD Agreement incorporated a Flow Chart that governs sequencing; final plat due after infrastructure completion, not within one year. Ordinance §9‑806 makes the PUD null if final plat not submitted within one year of preliminary approval. Court: The parties’ agreement and Flow Chart govern; the one‑year ordinance provision did not apply to this PUD.
Did failures to obtain/perform inspections justify termination? Inspection issues were addressed; engineers performed acceptance testing and issues were being remedied. Lonesome failed to follow inspection procedures and thus breached. Court: Although initial inspection lapses occurred, issues were resolved and were insufficient to justify termination.
Did Lonesome violate tree‑removal ordinance so as to justify termination? Grading plan showing clear‑cutting was submitted and approved during preliminary plat process; PUD Agreement waived tree removal fees and the parties treated grading plan as controlling. Lonesome clear‑cut without required tree‑removal permit, violating Ordinance §9‑703. Court: Parties’ conduct and the approved grading plan show the PUD terms controlled; retroactive enforcement of the tree ordinance was improper.
Was striking of Abita Springs’ economic‑loss expert and denial of new trial reversible error? Town: Exclusion of expert evidence was erroneous and justified a new trial. Lonesome: Town failed to proffer the excluded expert testimony, so appellate review is precluded. Court: Town did not proffer the expert’s testimony; exclusion not properly preserved for appeal.

Key Cases Cited

  • Jackson v. United Svcs. Auto. Ass'n Cas. Ins. Co., 1 So.3d 512 (La. App. 5 Cir. 2008) (trial court cannot consider evidence not formally introduced into the record)
  • Borcik v. Crosby Tugs, LLC, 222 So.3d 672 (La. 2017) (statutes must be interpreted in light of their purpose when literal reading yields absurd results)
  • Salinger Grp., Inc. v. City‑Parish of East Baton Rouge, 309 So.3d 373 (La. App. 1 Cir. 2020) (de novo review of statutory interpretation)
  • Strachan v. Eichin, 195 So.3d 61 (La. App. 1 Cir. 2016) (de novo review of contract interpretation; manifest‑error standard for factual findings relevant to contract interpretation)
  • Cajun Constructors, Inc. v. Fleming Const. Co., Inc., 951 So.2d 208 (La. App. 1 Cir. 2006) (contract amendments/cancellations require mutual consent unless law provides otherwise)
  • L & A Contracting Co., Inc. v. Ram Indus. Coatings, Inc., 762 So.2d 1223 (La. App. 1 Cir. 2000) (same principle regarding unilateral contract modification)
Read the full case

Case Details

Case Name: Lonesome Development, LLC v. Town of Abita Springs
Court Name: Louisiana Court of Appeal
Date Published: Jun 29, 2022
Citations: 343 So.3d 831; 2021CA1463
Docket Number: 2021CA1463
Court Abbreviation: La. Ct. App.
Log In
    Lonesome Development, LLC v. Town of Abita Springs, 343 So.3d 831