History
  • No items yet
midpage
Lockheed Martin Aeronautics Company
ASBCA No. 62505, 62506
| A.S.B.C.A. | Jun 24, 2021
Read the full case

Background

  • Two undefinitized F-16 upgrade contracts (Foreign Military Sales) awarded to Lockheed Martin (LM); each contained a "not to exceed" amount and clauses permitting the CO to unilaterally definitize price if parties failed to agree.
  • LM submitted definitization proposals; after years the parties did not agree and the contracting officer (CO) unilaterally set final prices by modification in February 2020.
  • LM did not present a claim to the CO; instead it filed direct appeals to the Armed Services Board of Contract Appeals (ASBCA) in May 2020 challenging the unilateral definitizations.
  • The Air Force moved to dismiss for lack of jurisdiction, arguing LM failed to exhaust the Contract Disputes Act (CDA) administrative process (i.e., file a CO claim). The government relied principally on Bell Helicopter Textron (ASBCA precedent) that a unilateral definitization is not a government claim.
  • The ASBCA majority concluded Bell Helicopter remains binding and dismissed for lack of jurisdiction; Judge Clarke dissented, arguing subsequent case law ("other relief") and practice effectively make unilateral definitization a government claim.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether a CO's unilateral contract definitization is a "government claim" appealable directly to the Board LM: Definitization is a CO final decision constituting a government claim under the Disputes clause (including the "other relief" category); thus LM may appeal directly Gov: Bell Helicopter controls — unilateral definitization merely establishes the contract price under the contract and is contract administration, not a government claim; contractor must present a claim to the CO first Majority: Dismissed for lack of jurisdiction; unilateral definitization is not a government claim under binding Bell Helicopter
Whether later authority (General Electric/Garrett, Todd Construction) has effectively overruled Bell Helicopter LM: Subsequent Federal Circuit and ASBCA decisions broadened "claim" (esp. "other relief") so Bell is no longer sound Gov: Those cases did not address or overrule Bell; they are distinguishable and do not change Bell's core reasoning Majority: Those authorities did not abrogate Bell; they do not compel treating definitization as a government claim
Whether analogies (terminations, CAS findings, data‑rights, unilateral indirect‑rate determinations) require treating definitization as a claim LM: Similar non‑monetary government actions have been treated as claims; definitization should be analogous Gov: Distinguishable — many analogous rulings involve taking money or property or directing additional performance, unlike routine price setting under a contract clause Majority: Analogs are not dispositive; key differences mean they don't overturn Bell
Whether the Board may depart from Bell Helicopter absent a higher‑court overruling or SDG action LM: Board should treat Bell as superseded by later law and practice Gov: Precedent binds; only SDG or Federal Circuit can overrule Board precedent Majority: The Board must follow Bell unless authoritatively overruled; it declines to do so here

Key Cases Cited

  • Garrett v. General Elec. Co., 987 F.2d 747 (Fed. Cir. 1993) (affirms that certain non‑monetary CO directives can be "other relief" constituting a government claim)
  • Todd Construction v. United States, 656 F.3d 1306 (Fed. Cir. 2011) (broad reading of "relating to" language; CDA jurisdiction extends to claims connected to contract performance)
  • Alliant Techsystems, Inc. v. United States, 178 F.3d 1260 (Fed. Cir. 1999) (non‑monetary claims can provide jurisdictional basis)
  • Malone d/b/a Precision Cabinet Co. v. United States, 849 F.2d 1441 (Fed. Cir. 1988) (termination for default is a government claim)
  • L‑3 Communications Integrated Sys. L.P. v. United States, 132 Fed. Cl. 325 (Ct. Fed. Cl. 2017) (contractor required to present a certified claim to the CO where monetary losses were alleged from unilateral definitization)
  • Lighting Control Ballast, LLC v. Phillips Elecs. N. Am. Corp., 744 F.3d 1272 (Fed. Cir. 2014) (discussion of when earlier precedent may be treated as overruled)
Read the full case

Case Details

Case Name: Lockheed Martin Aeronautics Company
Court Name: Armed Services Board of Contract Appeals
Date Published: Jun 24, 2021
Docket Number: ASBCA No. 62505, 62506
Court Abbreviation: A.S.B.C.A.