History
  • No items yet
midpage
2:19-cv-00389
C.D. Cal.
Sep 16, 2020
Read the full case

Background

  • Consolidated action arising from government construction projects: Moffett Field roofing (original prime BARA), Vandenberg HVAC (original prime FSG) and multiple Vandenberg Fire Alarm projects (including TLF).
  • F&D (Fidelity and Deposit Co. of Maryland) was surety after general contractors (BARA/FSG) defaulted; F&D signed ratification agreements with Kudsk and later retained Vertex to complete work.
  • Kudsk (Larry J. Kudsk dba Larry Kudsk Construction Services) sued for unpaid subcontract balances, extra work, and extended overhead; also brought a Miller Act claim for Moffett Field.
  • Defendants (Vertex and F&D) argued Kudsk abandoned HVAC work and sought completion costs; Vertex denied contractual duties to obtain certain Notices to Proceed on the TLF fire alarm project.
  • After trial, court awarded Kudsk $93,190.50 (Moffett Field) and $236,910.89 (Vandenberg HVAC), denied his fire-alarm claims (including TLF lost profits/administrative charges), and dismissed F&D’s counterclaim for completion costs.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Miller Act recovery for Moffett Field Kudsk performed work and is owed unpaid balance under Miller Act payment bond F&D argued offsets due to DOL withhold and delays in clearing condition Judgment for Kudsk: $93,190.50; no offset proven by F&D
Substantial performance on HVAC / termination Kudsk substantially performed or was excused by Vertex/Air Force conduct and delays F&D/Vertex said Kudsk abandoned work and was terminated for nonperformance Court found substantial performance/excuse; awarded $236,910.89 on HVAC
Extra work / change orders on HVAC Extra work requested/required by Air Force/Vertex and outside original scope; Kudsk entitled to compensation Defendants argued those items were within contract or unsupported Court found extra work claims valid and payable
F&D counterclaim for completion costs / third-party beneficiary claim N/A (counterclaim against Kudsk denied) F&D claimed it was third-party beneficiary and incurred costs completing HVAC after termination Court rejected F&D damages proof and awarded nothing on counterclaim
TLF Fire Alarm — pre-Notice charges and lost profits Kudsk performed preparatory/admin work and Vertex had duty to obtain Notice to Proceed; therefore Kudsk is entitled to compensation and lost profits Vertex/F&D argued no Notice to Proceed issued and no contractual duty to procure it; no entitlement without NTP Court held no contractual duty and denied payment for administrative work and lost profits on TLF

Key Cases Cited

  • Taylor Const. Inc. v. ABT Service Corp., Inc., 163 F.3d 1119 (9th Cir. 1998) (measure of recovery under the Miller Act is the sums due under the bonded contract)
  • United States ex rel. Sherman v. Carter, 353 U.S. 210 (U.S. 1957) (Miller Act policy obligates sureties to make good defaulting contractors' obligations)
  • Tolstoy Constr. Co. v. Minter, 78 Cal. App. 3d 665 (Cal. Ct. App. 1978) (California recognizes the doctrine of substantial performance)
Read the full case

Case Details

Case Name: Larry J. Kudsk v. Federal Solutions Group, Inc.
Court Name: District Court, C.D. California
Date Published: Sep 16, 2020
Citation: 2:19-cv-00389
Docket Number: 2:19-cv-00389
Court Abbreviation: C.D. Cal.
Log In
    Larry J. Kudsk v. Federal Solutions Group, Inc., 2:19-cv-00389