2:19-cv-00389
C.D. Cal.Sep 16, 2020Background
- Consolidated action arising from government construction projects: Moffett Field roofing (original prime BARA), Vandenberg HVAC (original prime FSG) and multiple Vandenberg Fire Alarm projects (including TLF).
- F&D (Fidelity and Deposit Co. of Maryland) was surety after general contractors (BARA/FSG) defaulted; F&D signed ratification agreements with Kudsk and later retained Vertex to complete work.
- Kudsk (Larry J. Kudsk dba Larry Kudsk Construction Services) sued for unpaid subcontract balances, extra work, and extended overhead; also brought a Miller Act claim for Moffett Field.
- Defendants (Vertex and F&D) argued Kudsk abandoned HVAC work and sought completion costs; Vertex denied contractual duties to obtain certain Notices to Proceed on the TLF fire alarm project.
- After trial, court awarded Kudsk $93,190.50 (Moffett Field) and $236,910.89 (Vandenberg HVAC), denied his fire-alarm claims (including TLF lost profits/administrative charges), and dismissed F&D’s counterclaim for completion costs.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Miller Act recovery for Moffett Field | Kudsk performed work and is owed unpaid balance under Miller Act payment bond | F&D argued offsets due to DOL withhold and delays in clearing condition | Judgment for Kudsk: $93,190.50; no offset proven by F&D |
| Substantial performance on HVAC / termination | Kudsk substantially performed or was excused by Vertex/Air Force conduct and delays | F&D/Vertex said Kudsk abandoned work and was terminated for nonperformance | Court found substantial performance/excuse; awarded $236,910.89 on HVAC |
| Extra work / change orders on HVAC | Extra work requested/required by Air Force/Vertex and outside original scope; Kudsk entitled to compensation | Defendants argued those items were within contract or unsupported | Court found extra work claims valid and payable |
| F&D counterclaim for completion costs / third-party beneficiary claim | N/A (counterclaim against Kudsk denied) | F&D claimed it was third-party beneficiary and incurred costs completing HVAC after termination | Court rejected F&D damages proof and awarded nothing on counterclaim |
| TLF Fire Alarm — pre-Notice charges and lost profits | Kudsk performed preparatory/admin work and Vertex had duty to obtain Notice to Proceed; therefore Kudsk is entitled to compensation and lost profits | Vertex/F&D argued no Notice to Proceed issued and no contractual duty to procure it; no entitlement without NTP | Court held no contractual duty and denied payment for administrative work and lost profits on TLF |
Key Cases Cited
- Taylor Const. Inc. v. ABT Service Corp., Inc., 163 F.3d 1119 (9th Cir. 1998) (measure of recovery under the Miller Act is the sums due under the bonded contract)
- United States ex rel. Sherman v. Carter, 353 U.S. 210 (U.S. 1957) (Miller Act policy obligates sureties to make good defaulting contractors' obligations)
- Tolstoy Constr. Co. v. Minter, 78 Cal. App. 3d 665 (Cal. Ct. App. 1978) (California recognizes the doctrine of substantial performance)
