History
  • No items yet
midpage
Lake Charles Xxv, LLC v. United States
118 Fed. Cl. 717
Fed. Cl.
2014
Read the full case

Background

  • GSA awarded contract GS-07B-16093 to Carotex to design, build, and lease a SSA office in Lake Charles, LA.
  • Lake Charles LLC substituted as lessee via SLA No. 1 and notice to proceed issued before completion of construction drawings.
  • DIDs were issued but not incorporated into the contract through an SLA; SLA No. 2 (Nov. 8, 2007) set a new completion schedule to Feb. 28, 2008.
  • GSA issued cure notices following delays; construction progress remained minimal; satellite schedule and site inspections were pursued.
  • GSA terminated for default on June 5, 2008; Lake Charles claimed delay, permitting, and weather issues; government pursued reprocurement costs and liquidated damages.
  • CO denied Lake Charles’ certified claim in 2011; suit filed in 2009; court granted partial summary judgment to government and denied plaintiff’s cross-motion.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
No-waiver clause effect on original terms Lake Charles argues no-waiver preserves rights to original DID and review provisions. SLA No. 2 superseded original terms; no-waiver clause cannot preserve pre-SLA rights. No; SLA No. 2 superseded, no-waiver clause did not preserve pre-SLA rights.
Whether delays were excusable Delays were excusable under 48 C.F.R. 552.270-18 and the contract's terms. Delays were not timely noticed and SLA No. 2 superseded prior conditions; delays not excused. Not excused; no timely notice and SLA No. 2 superseded original duties.
Whether plaintiff showed bad faith GSA acted with bad faith to terminate to relocate SSA; evidence shows intent to injure. No clear intent to injure; actions within contract rights and ordinary contract administration. No bad faith; government actions consistent with contract rights.
Whether termination for default was proper Termination was improper because government delays and SLA issues nullified performance obligations. Termination proper due to plaintiff’s material breach and failure to meet SLA No. 2 schedule. Proper termination for default; no material factual dispute on the core issues.

Key Cases Cited

  • Long Island Savings Bank, FSB v. United States, 503 F.3d 1234 (Fed. Cir. 2007) (no-waiver clause not categorically unwaivable; facts matter)
  • Westfeld Holdings, Inc. v. United States, 407 F.3d 1352 (Fed. Cir. 2005) (no-waiver clause enforcement varies by case)
  • Public Service Co. v. United States, 91 Fed. Cl. 363 (Fed. Cl. 2010) (court noted potential waiver considerations but required strong evidence)
Read the full case

Case Details

Case Name: Lake Charles Xxv, LLC v. United States
Court Name: United States Court of Federal Claims
Date Published: Oct 15, 2014
Citation: 118 Fed. Cl. 717
Docket Number: 1:09-cv-00363
Court Abbreviation: Fed. Cl.