History
  • No items yet
midpage
L & H Construction Co. v. Circle Redmont, Inc.
55 So. 3d 630
Fla. Dist. Ct. App.
2011
Read the full case

Background

  • L&H Construction contracted with Circle Redmont to manufacture a cast-iron staircase and a plank glass flooring system for the Thomas Edison site renovation for the National Park Service, with L&H as general contractor.
  • Proposals evolved; initial terms included install, but a revised progress-payment schedule shifted to payment upon supervision of installation.
  • Redmont signed a subcontract submitted by L&H that incorporated the February 26, 2004 final proposal's scope, but it listed the final payment milestone as due upon Completion, not supervision.
  • Redmont claimed the installation term was an error and that the parties intended only installation supervision, while L&H believed installation was included based on the final proposal and signed subcontract.
  • Redmont refused to ship or install the materials unless L&H paid, and later sold the installation to NPS after termination of L&H; trial court found the February 26, 2004 proposal governed and that the installation term was a mutual mistake, but the court’s judgment was internally inconsistent and did not support a breach finding against L&H.
  • We reverse the final judgment finding L&H in breach.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the final contract is ambiguous on installation vs supervision. L&H argues the final proposal and signed subcontract show installation was included. Redmont contends the installation term was a scrivener's error and only supervision was intended. Ambiguous contract; parol evidence permitted to resolve mutual mistake.
Whether the court properly permitted reformation based on mutual mistake. L&H asserts no mutual mistake; terms reflect installation. Redmont asserts mutual mistake due to scrivener's error. Mutual mistake proven by clear and convincing evidence; reformation appropriate.
Whether evidence post-impasse was properly excluded as settlement/attorney communications. Evidence post-impasse should clarify performance and breach. That evidence is excluded as settlement/attorney communications. Trial court erred in excluding post-impasse evidence for breach proof.
Whether Redmont breached by refusing to ship or install prior to full payment. L&H argues no breach; disputes over payment terms pending. Redmont asserts non-performance due to nonpayment and dispute. No proven breach; record insufficient to sustain breach finding.
Whether damages/claims arising after impasse could sustain a verdict against L&H. Terminates with dispute unresolved; damages depend on installation. Damages tied to late performance and final sale to NPS. Insufficient evidence of breach damages; reversal appropriate.

Key Cases Cited

  • Acumen Constr., Inc. v. Neher, 616 So. 2d 98 (Fla. 2d DCA 1993) (threshold contract formation question; assent implied by conduct)
  • Altman Cooling Corp. v. Fla. Heat & Power, Inc., 305 So. 2d 225 (Fla. 4th DCA 1974) (interpretation of contracts; intent governs)
  • Commerce P'ship 8098 Ltd. P'ship v. Equity Contracting Co., 695 So. 2d 383 (Fla. 4th DCA 1997) (ambiguous terms; course of dealing considered)
  • Haenal v. U.S. Fidelity & Guar. Co., 88 So. 2d 888 (Fla.1956) (court may interpret contracts; intent controls)
  • Blackhawk Heating & Plumbing Co. v. Data Lease Fin. Corp., 302 So. 2d 404 (Fla.1974) (parol evidence may aid in determining intent; mutual/misunderstanding)
  • Providence Square Ass'n, Inc. v. Biancardi, 507 So. 2d 1366 (Fla.1987) (mutual mistake; scrivener’s error; admissibility of parol evidence)
  • BrandsMart U.S.A. of West Palm Beach, Inc. v. DR Lakes, Inc., 901 So. 2d 1004 (Fla. 4th DCA 2005) (clear and convincing standard for mutual-mistake relief)
Read the full case

Case Details

Case Name: L & H Construction Co. v. Circle Redmont, Inc.
Court Name: District Court of Appeal of Florida
Date Published: Feb 4, 2011
Citation: 55 So. 3d 630
Docket Number: 5D09-3450
Court Abbreviation: Fla. Dist. Ct. App.