History
  • No items yet
midpage
2018 Ohio 5332
Ohio Ct. App.
2018
Read the full case

Background

  • In Feb 2017 USA Insulation contracted to insulate Ruby Kumar’s exterior walls for $6,213.96 (senior discount applied) financed by an interest-free Wells Fargo loan; USA was paid by Wells Fargo.
  • USA Insulation performed the work in March 2017; Kumar complained of cold spots and hired third parties to perform infrared diagnostics, spending about $550.
  • USA sent a service representative on March 20, 2017, who identified a few spots needing follow-up; Kumar initially refused to schedule further service.
  • A service visit occurred in March 2018 (after suit), producing a signed service ticket listing remaining work (estimated at 3–4 hours; about 5–10% of the job). USA stated it would return to complete any voids.
  • Kumar sued in small claims (March 6, 2018) seeking approximately $6,000 for incomplete and fraudulent work; trial was to the court, Kumar proceeded pro se, and the court entered judgment for USA Insulation.
  • The court found Kumar failed to prove her case by a preponderance of the evidence; on appeal she argued (1) the court wrongly required proof of out-of-pocket payments to Wells Fargo for damages and (2) USA’s admission of incomplete performance established breach.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether USA’s alleged admission of incomplete performance established breach of contract Kumar: USA admitted incomplete performance and therefore is liable for breach USA: Any remaining work was minor (substantial performance) and further completion was prevented by Kumar’s refusal to allow access Court: No breach — evidence showed substantial performance (only 5–10% remained) and further work was impeded by Kumar
Whether plaintiff was required to present proof of payments to Wells Fargo to establish contract damages Kumar: Court improperly required evidence of her payments to Wells Fargo to measure damages USA: The court reasonably probed payments to determine amounts paid to USA and whether damages were owed; plaintiff failed to prove breach or quantify damages Court: No error — plaintiff failed to establish breach and did not meet burden to prove damages with reasonable certainty; general verdict presumed correct absent requested findings of fact

Key Cases Cited

  • Luntz v. Stern, 135 Ohio St. 225 (1939) (when facts are undisputed, whether they constitute performance or breach is a question of law)
  • Cleveland Neighborhood Health Servs., Inc. v. St. Clair Builders, Inc., 64 Ohio App.3d 639 (1989) (substantial performance doctrine; slight omissions do not always constitute breach)
  • Ashley v. Henahan, 56 Ohio St. 559 (1897) (substantial performance entitles party to payment absent willful omission)
  • Kichler’s, Inc. v. Persinger, 24 Ohio App.2d 124 (1970) (minor departures, omissions and inadvertencies should be disregarded under substantial performance)
  • Lucarell v. Nationwide Mut. Ins. Co., 152 Ohio St.3d 453 (2018) (breach defined as failure without legal excuse to perform when performance is due)
  • Schulke Radio Prod., Ltd. v. Midwestern Broadcasting Co., 6 Ohio St.3d 436 (1983) (damages aim to place injured party in position they would have occupied absent breach)
Read the full case

Case Details

Case Name: Kumar v. USA Insulation
Court Name: Ohio Court of Appeals
Date Published: Dec 31, 2018
Citations: 2018 Ohio 5332; 127 N.E.3d 344; NO. 2018-L-058
Docket Number: NO. 2018-L-058
Court Abbreviation: Ohio Ct. App.
Log In
    Kumar v. USA Insulation, 2018 Ohio 5332