History
  • No items yet
midpage
KLE Construction, LLC v. Twalker Development, LLC
2016 ND 229
N.D.
2016
Read the full case

Background

  • KLE Construction performed civil development work (dirt work, engineering/surveying, equipment hauling) on property owned by Twalker during negotiations for payment in four lots; no written contract was executed.
  • Twalker terminated KLE’s services, completed further development, and did not pay KLE for the work performed.
  • KLE sued for breach of contract, unjust enrichment, and forbearance; after a bench trial the district court dismissed the breach and forbearance claims but found unjust enrichment and awarded damages of $90,857 (judgment entered for $87,958.74 after offsets).
  • Twalker appealed, arguing (1) KLE had an adequate remedy at law (could have filed a construction/mechanic’s lien) so unjust enrichment was improper, and (2) the damages award should be limited to the defendant’s enrichment rather than plaintiff’s impoverishment.
  • The Supreme Court reviewed findings for clear error and conclusions of law de novo, and affirmed the district court judgment in all respects.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Was unjust enrichment available where no written contract existed? KLE: unjust enrichment applies because Twalker retained benefits and no contract remedy existed. Twalker: KLE had an adequate legal remedy (mechanic’s lien/foreclosure), so unjust enrichment is unavailable. Affirmed: Twalker failed to preserve the lien argument below; court did not address lien availability and upheld unjust enrichment.
Did KLE prove elements of unjust enrichment (enrichment, impoverishment, connection, lack of justification, lack of legal remedy)? KLE: presented evidence showing Twalker was enriched by KLE’s work and KLE was impoverished. Twalker: argued KLE failed to show Twalker was enriched by the services. Affirmed: district court found each element satisfied as to specific services (dirt work, engineering, hauling).
Was the damages award improperly calculated by focusing on plaintiff’s loss rather than defendant’s gain? KLE: sought recovery for employee costs, equipment use, mobilization, engineering, and management fee. Twalker: damages should be limited to value of defendant’s enrichment, not full plaintiff loss. Affirmed: court awarded damages only for services it found enriched Twalker; award was within evidentiary range and not clearly erroneous.
Are appellate attorney’s fees warranted because the appeal is frivolous? KLE: appeal is frivolous and fees should be awarded. Twalker: appeal had merit. Denied: Court found the appeal not flagrantly groundless or devoid of merit.

Key Cases Cited

  • Border Res., LLC v. Irish Oil & Gas, Inc., 869 N.W.2d 758 (N.D. 2015) (standard of review for bench trials and credibility findings)
  • McColl Farms, LLC v. Pflaum, 837 N.W.2d 359 (N.D. 2013) (elements of unjust enrichment explained)
  • Ritter, Laber and Assoc., Inc. v. Koch Oil, Inc., 680 N.W.2d 634 (N.D. 2004) (unjust enrichment requires restitution of benefits received in absence of contract)
  • A & A Metal Bldgs. v. I-S, Inc., 274 N.W.2d 183 (N.D. 1978) (damages measured by defendant’s unjust enrichment affirmed)
  • Prairie Supply, Inc. v. Apple Elec., Inc., 867 N.W.2d 335 (N.D. 2015) (damages finding as fact reviewed for clear error)
  • Valley Honey Co., LLC v. Graves, 666 N.W.2d 453 (N.D. 2003) (Supreme Court will not disturb a damages award unless it lacks evidentiary support)
  • Gray v. Berg, 878 N.W.2d 79 (N.D. 2016) (standard for awarding appellate fees for frivolous appeals)
Read the full case

Case Details

Case Name: KLE Construction, LLC v. Twalker Development, LLC
Court Name: North Dakota Supreme Court
Date Published: Dec 5, 2016
Citation: 2016 ND 229
Docket Number: 20160054
Court Abbreviation: N.D.