Kim Garrigus v. Chad Burnett D/B/A Heartland Garage, Inc.
2020 CA 000702
| Ky. Ct. App. | Jun 16, 2021Background
- Parties contracted on Dec. 31, 2018: Burnett/Heartland to build a 30' x 24' detached garage for $15,912; Garrigus paid a $10,912 retainer.
- Appellee installed forms and footers (left in place ~19 days) and poured the concrete foundation on Jan. 24–Feb. 13, 2019.
- During the pour Garrigus complained the foundation was in the wrong location and about the dimensions; Appellee said the pour could not be stopped; no further work was performed.
- Garrigus sued for breach of contract seeking recovery for removal/correction and related costs.
- Graves Circuit Court found no breach proven, accepted Appellee’s $5,661.80 cost for performed work, and awarded Garrigus the remaining retainer of $5,250.20.
- Garrigus appealed; the Court of Appeals affirmed, concluding the contract was silent as to placement and that Garrigus offered only her testimony to prove incorrect dimensions or placement.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether Appellee breached the construction contract by placing/pouring the foundation in the wrong location and to the wrong dimensions | The contract and photos show the garage was not placed as agreed, misaligned with driveway, over utilities, and foundation was smaller than 30' x 24' | Contract drawing does not specify placement; Appellee testified placement and dimensions were correct and work was performed as contracted | No breach — contract silent as to placement and plaintiff offered only her testimony to prove nonconformity; trial court's credibility findings upheld |
| Whether plaintiff failed to mitigate damages | Garrigus argued she suffered pecuniary loss and needed costs to remove/redo foundation | Appellee contended mitigation was not shown and, because no breach was proved, mitigation is moot | Moot / not reached on the merits because no breach was found; court noted plaintiff bore burden to show mitigation only if breach proved |
Key Cases Cited
- Kentucky Shakespeare Festival, Inc. v. Dunaway, 490 S.W.3d 691 (Ky. 2016) (unenforced written instrument is to be applied according to its terms when unambiguous)
- Barnett v. Mercy Health Partners-Lourdes, Inc., 233 S.W.3d 723 (Ky. App. 2007) (elements required to prove breach of contract)
- Owens-Corning Fiberglas Corp. v. Golightly, 976 S.W.2d 409 (Ky. 1998) (standard for reviewing factual findings under CR 52.01)
- Kentucky State Racing Comm’n v. Fuller, 481 S.W.2d 298 (Ky. 1972) (definition of substantial evidence standard)
- Cantrell Supply, Inc. v. Liberty Mut. Ins. Co., 94 S.W.3d 381 (Ky. App. 2002) (questions of law reviewed de novo)
- Lawson v. Loid, 896 S.W.2d 1 (Ky. 1995) (deference to trial judge on witness credibility under CR 52.01)
- Jones v. Marquis Terminal, Inc., 454 S.W.3d 849 (Ky. App. 2014) (burden on breaching party to prove plaintiff failed to mitigate damages)
