History
  • No items yet
midpage
448 S.W.3d 207
Ark. Ct. App.
2014
Read the full case

Background

  • Van Horn Construction (general contractor) subcontracted dirtwork for a Searcy water‑treatment plant expansion to Keith Capps Landscaping & Excavation for $131,700; subcontract required “class 7” fill placed in 6–9 inch lifts with compaction and testing per plans/specs.
  • Capps had a borrow pit containing shale (not class 7); parties disputed whether Van Horn told Capps shale would be acceptable and whether Capps saw the plans/specs before signing.
  • Tests of placed lifts repeatedly failed due to moisture content and insufficient processing of shale; Capps reworked lifts extensively and allegedly placed lifts too thickly, increasing time and cost.
  • Van Horn offered options (including splitting cost of alternative B stone); Capps declined, stopped work, and refused to return after a 48‑hour notice under the subcontract allowing termination for failure to perform.
  • Van Horn completed the work using others and its own resources, incurring completion costs and liquidated/delay damages from the owner; it sued for breach of contract and recovered $245,632 (completion costs plus allocated delay damages), plus costs and fees.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Capps breached the subcontract by failing to perform and refusing to complete the work Van Horn: Capps failed to comply with plans/specs (lifts, compaction, material processing) and abandoned the job after notice Capps: shale could not meet specs under weather conditions; Van Horn permitted or induced use of shale and breached by refusing change order; performance impossible Court: Factfinder credited Van Horn; Capps breached and ultimately refused to complete; prior negotiations merged into subcontract
Whether Van Horn’s damages were excessive/unreasonable Van Horn: Damages measured by cost to complete minus contract balance and include allocated owner delay costs; provided itemized evidence Capps: Completion costs were disproportionate (over 2.5× subcontract) and thus unreasonable Court: Used standard measure (cost to complete less contract price); Van Horn’s itemized costs and testimony supported award; damages not clearly erroneous
Whether fraud in procurement vitiates enforcement of subcontract Van Horn: N/A Capps: Argues Van Horn committed fraud by inducing use of shale Court: Fraud argument not raised below, thus waived on appeal; no consideration of new fraud claim
Whether credibility/findings were clearly erroneous under bench‑trial standard Van Horn: Trial court’s factual findings supported by witnesses, documents, and testing results Capps: Contends evidence shows impossibility and that trial miscredited testimony Court: Appellate review deferred to factfinder; no firm conviction of mistake—findings not clearly erroneous

Key Cases Cited

  • Schwyhart v. J.B. Hunt, LLC, 436 S.W.3d 173 (Ark. Ct. App. 2014) (elements of breach and standard for proving contract claim in bench trial)
  • MDH Builders, Inc. v. Nabholz Constr. Corp., 70 Ark. App. 284, 17 S.W.3d 97 (Ark. Ct. App. 2000) (measure of damages: cost to complete less contract price)
Read the full case

Case Details

Case Name: Keith Capps Landscaping & Excavation, Inc. v. Van Horn Construction, Inc.
Court Name: Court of Appeals of Arkansas
Date Published: Nov 12, 2014
Citations: 448 S.W.3d 207; 2014 Ark. App. 638; CV-14-309
Docket Number: CV-14-309
Court Abbreviation: Ark. Ct. App.
Log In