History
  • No items yet
midpage
100 Fed. Cl. 8
Fed. Cl.
2011
Read the full case

Background

  • Plaintiff K-Con Building Systems, Inc. contracted with the Coast Guard for Port Huron, Michigan project under a GSA schedule-based award.
  • The contract required phased design submissions (50%, 90%, 100%) and total completion within 300 days of award.
  • Coast Guard design specs included climate control, electrical, HVAC, and telecom room requirements, with drawings provided as guidelines.
  • The contract contained a liquidated damages clause of $589 per day for delay, calculated using Coast Guard overhead and travel/admin costs.
  • Coast Guard initially approved 50% design in June 2004 and later withheld retainage, communicating ongoing schedule concerns and potential changes.
  • Contrary to expectations, substantial design revisions and Coast Guard comments followed, some of which were argued by K-Con to constitute changes beyond the Scope of Services.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Enforceability of liquidated damages rate as a reasonable forecast Rate bears no reasonable relation to probable damages Rate reasonable and enforceable given anticipated overheads Enforceable; not a penalty
Remission of liquidated damages due to constructive suspension Coast Guard constructively suspended work delaying performance No suspension sufficient to remit liquidated damages Delay not proven on the critical path; remission denied for now
Excusable delay and remission of damages Coast Guard delays on changes excuse delay No proof delay on critical path; need trial Insufficient proof on critical path; remission denied at this stage
Whether Coast Guard comments constituted changes triggering changes clause Comments imposed extrinsic requirements altering contract Comments were reminders to comply with current standards Genuine issues of material fact on notice and whether comments are changes
Notice requirements for changes under the Changes clause Coast Guard's conduct and notices implied changes Notice requirements not clearly satisfied Genuine issues of material fact; unresolved.

Key Cases Cited

  • Priebe & Sons, Inc. v. United States, 332 U.S. 407 (U.S. 1947) (liquidated damages judged as of contract formation; reasonable forecast required)
  • Jennie-O Foods, Inc. v. United States, 580 F.2d 400 (Ct.Cl. 1978) (usefulness of liquidated damages when damages uncertain)
  • DJ Mfg. Corp. v. United States, 86 F.3d 1130 (Fed.Cir. 1996) (bears burden to show liquidated damages are not a penalty; reasonableness standard)
  • Bethlehem Steel Co. v. United States, 205 U.S. 105 (1907) (enforce liquidated damages without proof of actual damages; reasonableness at formation)
  • P & D Contractors, Inc. v. United States, 25 Cl.Ct. 237 (Cl.Ct. 1992) (reasonableness determined at contract formation; timing of challenge discussed)
Read the full case

Case Details

Case Name: K-Con Building Systems, Inc. v. United States
Court Name: United States Court of Federal Claims
Date Published: Aug 19, 2011
Citations: 100 Fed. Cl. 8; 2011 WL 3634164; 2011 U.S. Claims LEXIS 1757; No. 05-1054C
Docket Number: No. 05-1054C
Court Abbreviation: Fed. Cl.
Log In
    K-Con Building Systems, Inc. v. United States, 100 Fed. Cl. 8