History
  • No items yet
midpage
97 Fed. Cl. 41
Fed. Cl.
2011
Read the full case

Background

  • K-Con Building Systems, Inc. sued the Coast Guard over a Elizabeth City project arising from a design/build contract under a GSA schedule, seeking partial summary judgment on liquidated damages.
  • The contract contained a liquidated damages clause of $551 per day for delays beyond the completion date, governed by FAR subpart 11.5 and related guidelines.
  • The contracting officer used a preexisting Coast Guard method with two cost categories (travel/diem/inspections and administrative costs) to forecast damages that would be incurred if delayed.
  • Delays occurred due to start-up scheduling, steel shortages, and coordination issues with government-owned equipment; the completion date was repeatedly extended, but plaintiff did not meet the final deadlines.
  • In November 2004–March 2005 the Coast Guard considered delaying termination, then terminated for default in March 2005, proceeding to reprocurement with Viteri Construction.
  • Plaintiff moved for remission of liquidated damages, while the Coast Guard sought to collect damages and retain the unpaid contract balance.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the liquidated damages rate is an unenforceable penalty. K-Con argues rate bears no reasonable relation to anticipated costs. Coast Guard contends rate is reasonable as a forecast of damages and consistent with precedent. Enforceable; rate reasonable under governing law.
Whether administrative costs are properly included as liquidated damages components. These costs are overhead not tied to delay and cannot be damages. Administrative costs forecast additional Coast Guard work caused by delay and are recoverable. Included; admissible as probable delay damages.
Whether the Elizabeth City rate components were reasonable and consistently applied. Inconsistencies and use of a Coast Guard instruction not suited for this purpose undermine reasonableness. Variations reflect project scope and timing; no basis to deem rate unreasonable for this contract. No reversible error; components deemed reasonable for this contract.
Whether plaintiff is entitled to remission of liquidated damages for excusable delay. Delays were concurrent with Coast Guard delays; should be excusable and remission granted. Plaintiff bears burden to prove excusable delay on critical path and concurrent delays are not shown. Remission denied; plaintiff failed to prove excusable delay on the critical path.
Whether the delay issues should be decided now or stayed for the other related cases. Court should decide ongoing issues promptly; delays may affect other contracts. Stay appropriate to coordinate with St. Petersburg and Port Huron matters. Court stayed disposition of related cases pending further proceedings.

Key Cases Cited

  • Priebe & Sons, Inc. v. United States, 332 U.S. 407 (1947) (liquidated damages must be a reasonable forecast at time of contract)
  • Bethlehem Steel Co. v. United States, 205 U.S. 105 (1907) (enforcement of liquidated damages without proof of actual damages)
  • DJ Mfg. Corp. v. United States, 86 F.3d 1130 (Fed. Cir. 1996) (court will enforce reasonable liquidated damages; will not inquire into officer’s method)
  • P & D Contractors, Inc. v. United States, 25 Cl.Ct. 237 (Cl. Ct. 1992) (reasonableness of liquidated damages determined at contract formation)
  • Mega Construction Co. v. United States, 29 Fed.Cl. 396 (Fed. Cl. 1993) (reasonableness analysis anchored in contractual formation conditions)
Read the full case

Case Details

Case Name: K-Con Building Systems, Inc. v. United States
Court Name: United States Court of Federal Claims
Date Published: Jan 24, 2011
Citations: 97 Fed. Cl. 41; 2011 U.S. Claims LEXIS 20; 2011 WL 228667; No. 05-914C
Docket Number: No. 05-914C
Court Abbreviation: Fed. Cl.
Log In
    K-Con Building Systems, Inc. v. United States, 97 Fed. Cl. 41