History
  • No items yet
midpage
Jurgensen Co. v. Fairborn
2015 Ohio 5478
Ohio Ct. App.
2015
Read the full case

Background

  • Fairborn solicited bids in 2006 for a multi-street road-improvement project; Jurgensen submitted the successful low bid for $1,106,881.80 and performed asphalt work Aug–Nov 2006.
  • Fairborn’s contract documents included its own Construction and Material Specification Item 400 and incorporated by reference ODOT construction and material specifications when Fairborn’s specs did not cover an item; 2005 ODOT Specs were in effect.
  • ODOT Item 401.20 contains an asphalt-binder price-adjustment mechanism that can adjust contract prices if binder prices change; Fairborn’s documents referenced ODOT Item 401 only in the context of material/specification requirements for asphalt work.
  • After completion, asphalt prices rose and Jurgensen submitted a claim for $92,395.66 under an asphalt-binder price adjustment; Fairborn refused to pay and withheld retained-interest disputed separately.
  • Jurgensen sued for breach and declaratory relief; both parties moved for summary judgment. The trial court denied Jurgensen’s motion and granted Fairborn’s on the price-adjustment claim; Jurgensen appealed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether ODOT Item 401.20 (asphalt-binder price adjustment) was incorporated into the parties' contract Jurgensen: Fairborn Item 400 and the general incorporation clause brought in ODOT Item 401 (including 401.20), so the price-adjustment applies Fairborn: References to ODOT items govern construction/specifications only and do not modify express pricing/payment terms elsewhere in the contract Held: Not incorporated as an obligation to pay; Item 400 only incorporated material/specification requirements, not payment adjustments
Whether, even if incorporated, ODOT Item 401.20 imposed a duty on the owner (Fairborn) to pay the adjustment Jurgensen: Item 401.20 makes asphalt items eligible for adjustment and thus creates an entitlement Fairborn: Item 401.20’s language applies to the Department and describes eligibility and computation; it does not impose an owner-payment obligation Held: Even if incorporated, Item 401.20 does not impose an express obligation on the owner to pay; it speaks to eligibility and Department procedures only
Whether custom/usage of trade made the price-adjustment term part of the contract Jurgensen: Industry custom and past practice with public entities using ODOT specs led Jurgensen to reasonably expect price adjustments Fairborn: The express contract terms control; Jurgensen failed to present admissible evidence of a binding usage known to Fairborn Held: Usage-of-trade evidence insufficient in the summary-judgment record; express contract terms prevail
Appropriateness of summary judgment on contract interpretation Jurgensen: No genuine issue of material fact and contract interpretation is a question of law Fairborn: Same; cross-motions show parties agreed legal resolution appropriate Held: De novo review appropriate; contract language was clear and summary judgment for Fairborn on the price-adjustment claim was correct

Key Cases Cited

  • Comer v. Risko, 833 N.E.2d 712 (Ohio 2005) (standard of review for summary-judgment rulings: de novo)
  • Danis Clarkco Landfill Co. v. Clark Cty. Solid Waste Mgt. Dist., 653 N.E.2d 646 (Ohio 1995) (use of specifications and contract interpretation principles)
  • Skivolocki v. E. Ohio Gas Co., 313 N.E.2d 374 (Ohio 1974) (contract interpretation focused on parties’ intent as evidenced by language)
  • S. A. Ruebel & Co. v. Morr, 120 N.E.2d 605 (Ohio App. 1953) (definition of ‘‘specification’’ in road-improvement contracts)
  • Camargo Cadillac Co. v. Garfield Ent., Inc., 445 N.E.2d 1141 (Ohio App. 1982) (express contract terms prevail over custom or usage of trade)
Read the full case

Case Details

Case Name: Jurgensen Co. v. Fairborn
Court Name: Ohio Court of Appeals
Date Published: Dec 30, 2015
Citation: 2015 Ohio 5478
Docket Number: C-140556
Court Abbreviation: Ohio Ct. App.