History
  • No items yet
midpage
Jovan, Inc v. Municipio De Aguadilla
KLAN202500096
Tribunal De Apelaciones De Pue...
Mar 31, 2025
Read the full case

Background

  • Jovan, Inc. (“Jovan”) was contracted by the Municipality of Aguadilla for the construction of a historic archive and museum, with the project divided into permitting and construction phases.
  • Numerous contractual amendments were made as delays and design changes arose; Jovan sent multiple letters notifying the Municipality of delay-related costs (“extended overhead”) due to late approval of change orders.
  • The Municipality never contested Jovan’s extended overhead claims during the project, and some amendments explicitly did not bar additional claims for certain delays, while others waived such claims.
  • After substantial completion, Jovan sued for $412,160.72 in extended overhead due to delays attributed to the Municipality; the trial court awarded $446,603.12 for extended overhead and $24,500 for inspection/supervision costs that had been deducted by the Municipality.
  • The Municipality appealed, challenging the sufficiency of the evidence on both awards, and argued Jovan had accepted responsibility for supervision expenses under contract amendments.
  • No meaningful defense evidence was presented by the Municipality at trial on either issue.

Issues

Issue Plaintiff Argument Defendant Argument Held
Entitlement to extended overhead damages Delays caused by Municipality merited compensation per standard construction principles No contractual basis for such costs; Jovan also had delays For Jovan — Municipality’s delays justified the award
Proof of extended overhead damages Used expert testimony, extensive documentation; Municipality didn’t refute Insufficient proof/causal link, not all delays compensable For Jovan — evidence was sufficient; no rebuttal offered
Reimbursement of supervision/inspection costs Jovan only signed amendments under duress; not voluntarily assumed Jovan expressly assumed responsibility by amendment For Municipality — contractually assumed by Jovan
Effect of contract amendments waiving claims Clauses were null as contracts of adhesion or didn’t cover all change orders Express waivers bind Jovan under contract law Followed amendments’ express terms, no waiver where absent

Key Cases Cited

  • Morán v. Martí, 165 DPR 356 (P.R. 2005) (establishes presumption of correctness for trial court findings)
  • SLG Fernández-Bernal v. RAD-MAN, 208 DPR 310 (P.R. 2021) (deference to credibility assessments of trial courts)
  • Barreto Nieves v. East Coast, 213 DPR 852 (P.R. 2024) (standards for appellate court intervention in factual findings)
  • Master Concrete Corp. v. Fraya, SE, 152 DPR 616 (P.R. 2000) (discusses obligations and standard of care in construction contracts)
  • Constructora Bauzá, Inc. v. García López, 129 DPR 579 (P.R. 1991) (distinguishes obligations in construction contracts)
  • Johnson & Johnson Int’l Inc. v. Mun. San Juan, 172 DPR 840 (P.R. 2007) (limits on municipal contracting power)
  • Cacho Pérez v. Hatton Gotay, 195 DPR 1 (P.R. 2016) (finality and binding nature of unappealed judgments)
Read the full case

Case Details

Case Name: Jovan, Inc v. Municipio De Aguadilla
Court Name: Tribunal De Apelaciones De Puerto Rico/Court of Appeals of Puerto Rico
Date Published: Mar 31, 2025
Docket Number: KLAN202500096