History
  • No items yet
midpage
307 P.3d 942
Alaska
2013
Read the full case

Background

  • The Aleut Corporation terminated Troy Johnson, its chief executive officer, triggering a binding arbitration under Johnson's employment contract.
  • The contract contains a broad arbitration clause requiring arbitration for any disputes arising out of or relating to the agreement and/or Johnson's employment or termination.
  • At arbitration, the issues were whether The Aleut Corporation breached the contract by terminating Johnson and whether Johnson's alleged breach justified termination; the arbitrator awarded Johnson damages.
  • The Aleut Corporation sought to vacate the award in superior court, arguing the arbitrator decided an issue not submitted to arbitration and exceeded authority.
  • The superior court vacated the award; Johnson challenged that decision, and the Alaska Supreme Court reversed, holding the dispute was arbitrable and the arbitrator did not exceed authority.
  • The arbitrator concluded the contract would automatically extend unless the board canceled the extension and that Johnson's conduct did not constitute a proper cause; however, he found the board breached by failing to timely notify of cancellation.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Did the arbitrator exceed authority by addressing an unsubmitted issue? Johnson/arbitration submission supported by broad clause and claims. Arbitrator exceeded authority by addressing non-submitted issue. No; arbitrator reasonably interpreted arbitrable dispute and did not exceed powers.
Is the dispute arbitrable under the employment agreement's broad arbitration clause? Clause covers all disputes about the contract and employment; dispute is arbitrable. Dispute not limited to the precise claimed issue; arbitration should be narrowed. Yes; arbitration clause covers the dispute and it was arbitrable.
May arbitrator resolve arbitrable disputes on a basis different from that argued by the parties? Arbitrator may rely on contract interpretation and different rationale. Arbitrator must adhere to theories advanced by the parties. Yes; arbitrator may reach a different basis so long as dispute is arbitrable.
Should the superior court have vacated the award based on arbitrability and scope? Vacatur was improper; the award falls within arbitrable scope. Vacatur appropriate if arbitrator exceeded authority or misinterpreted scope. Vacatur reversed; award confirmed and fees vacated.

Key Cases Cited

  • Ahtna, Inc. v. Ebasco Constructors, Inc., 894 P.2d 657 (Alaska 1995) (arbitrator may rely on provisions not expressly argued if dispute arises under the contract)
  • OK Lumber Co. v. Alaska R.R. Corp., 123 P.3d 1076 (Alaska 2005) (arbitrator did not exceed authority by interpreting contract to resolve dispute)
  • Pub. Safety Emps. Ass'n v. State, 732 P.2d 1090 (Alaska 1987) (deference to arbitrator on questions submitted; public policy favors arbitration)
  • Marathon Oil Co. v. ARCO Alaska, Inc., 972 P.2d 595 (Alaska 1999) (arbitrator's scope and remedies; deference to arbitration decisions)
  • Sea Star Stevedore Co. v. Int'l Union of Operating Engineers, Local 302, 769 P.2d 428 (Alaska 1989) (arbitrator exceeds authority by addressing a question not submitted)
Read the full case

Case Details

Case Name: Johnson v. The Aleut Corporation
Court Name: Alaska Supreme Court
Date Published: Aug 23, 2013
Citations: 307 P.3d 942; 2013 WL 4500323; 36 I.E.R. Cas. (BNA) 760; 2013 Alas. LEXIS 110; 6813 S-14632
Docket Number: 6813 S-14632
Court Abbreviation: Alaska
Log In
    Johnson v. The Aleut Corporation, 307 P.3d 942