History
  • No items yet
midpage
John Jones, III v. National Marine Fisheries Serv
741 F.3d 989
9th Cir.
2013
Read the full case

Background

  • ORC sought four Section 404 permits near Coos Bay, Oregon, for mining chromite, garnet, and zircon sands; the Corps prepared an EA and issued a FONSI under NEPA instead of an EIS.
  • Woodlands challenged the EA and FONSI, arguing the Cr+6 generation risk was inadequately analyzed and that the FONSI was arbitrary due to uncertainty; they also challenged the Corps’ alternatives analysis.
  • The Corps relied on the BA, Mason Memorandum, and state permits (DEQ 401 and DOGAMI) to assess Cr+6 risk, concluding no significant impact and mandating monitoring.
  • A mitigation framework was provided through state permits, including potential suspension of mining if Cr+6 levels rose.
  • The Corps also considered cumulative impacts and alternative designs/sites, ultimately focusing on four sites and rejecting some as nonviable.
  • District court granted summary judgment for the Corps; on appeal, the Ninth Circuit upheld, affirming NEPA and CWA analyses.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
NEPA compliance for Cr+6 risk analysis Woodlands contends the EA relied on expert opinion without data and undervalued Cr+6 uncertainty. ORC argues the EA incorporated underlying data (Mason Memorandum) and monitored data; uncertainty did not require an EIS. NEPA satisfied; incorporation of data and monitoring supported a valid FONSI.
Need for an EIS due to Cr+6 uncertainty Woodlands claims substantial uncertainty required an EIS before permitting. Court should defer to agency findings where risks are unlikely and site conditions favor attenuation. FONSI proper; uncertainty did not mandate an EIS.
Cumulative impacts of future mining Woodlands asserts the Corps failed to analyze cumulative impacts of expanded mining along the coast. There is no reliable projection of future mining; analysis of speculative sites was premature. No required cumulative impacts analysis for speculative future mining.
Reasonableness of the Corps' alternatives analysis under CWA Woodlands argues SMaller designs were mischaracterized and financing considerations improperly shaped alternatives. Alternative sites were evaluated for practicability including cost and logistics; financing considerations are permissible. Alternatives analysis was proper and not in violation of the CWA.

Key Cases Cited

  • Nat. Ass’n of Home Builders v. Defenders of Wildlife, 551 U.S. 644 (2007) (deference for NEPA decisions; data reliance)
  • Klamath-Siskiyou Wildlands v. BLM, 387 F.3d 989 (9th Cir. 2004) (NEPA documents cannot rely solely on expert opinions)
  • Idaho Sporting Cong. v. Thomas, 137 F.3d 1146 (9th Cir. 1998) (data underlying EAs must be provided)
  • Northern Plains Res. Council v. Surface Transp. Bd., 668 F.3d 1067 (9th Cir. 2011) (monitoring as appropriate, not dismissal of risk)
  • Bering Strait Citizens for Responsible Res. Dev. v. U.S. Army Corps of Eng’rs, 524 F.3d 938 (9th Cir. 2008) (consideration of available alternatives; 404(b)(1) guidelines)
  • Lands Council v. Powell, 395 F.3d 1019 (9th Cir. 2005) (cumulative impacts analysis timing; reasonably foreseeable actions)
  • EPIC v. Forest Serv., 452 F.3d 1005 (9th Cir. 2006) (cumulative effects and data considerations in NEPA)
  • City of Sausalito v. O’Neill, 386 F.3d 1186 (9th Cir. 2004) (incorporation by reference of underlying data allowed)
  • Waterworth v. U.S. Army Corps of Eng’rs, 420 F.3d 440 (5th Cir. 2005) (mitigation as part of permitting decisions)
Read the full case

Case Details

Case Name: John Jones, III v. National Marine Fisheries Serv
Court Name: Court of Appeals for the Ninth Circuit
Date Published: Dec 20, 2013
Citation: 741 F.3d 989
Docket Number: 11-35954
Court Abbreviation: 9th Cir.