History
  • No items yet
midpage
John A. Becker Co. v. Jedson Eng'g, Inc.
121 N.E.3d 788
| Ohio Ct. App. | 2018
Read the full case

Background

  • Jedson (general contractor) purchased lighting materials from Becker; Jedson signed Becker’s Credit Application on April 20, 2016 and submitted a Purchase Order on April 21 that included an arbitration clause favoring arbitration in Cincinnati at buyer’s option.
  • Becker delivered materials June 7, 2016; Jedson failed to pay after it experienced payment disputes with its owner (CP Kelco), leaving Becker unpaid.
  • Related multi-party litigation was filed in Oklahoma by another supplier; Jedson later filed (and voluntarily dismissed) third-party claims against Becker in the Oklahoma action.
  • Becker sued Jedson in Ohio (Dec. 2016) for breach of contract; Jedson initially sought extensions, moved to dismiss or stay (forum non conveniens, comity, failure to join CP Kelco), and did not invoke arbitration for >9 months.
  • While the Ohio court held the contract likely granted Jedson a right to arbitrate, the trial court denied a stay, finding Jedson waived arbitration by actively participating in litigation and delaying invocation of arbitration; appellate court affirmed.

Issues

Issue Plaintiff's Argument (Becker) Defendant's Argument (Jedson) Held
Whether Jedson waived the contractual right to arbitrate Becker argued Jedson implicitly waived arbitration by litigating and delaying assertion of arbitration Jedson argued it retained the contractual right and timely sought stay pending arbitration once appropriate Court held Jedson waived arbitration based on totality of circumstances (delay >9 months, active litigation participation, inconsistent acts)
Whether arbitration clause was part of the parties’ contract (Becker cross-appeal) Becker argued its quote + credit agreement were the offer and Jedson’s PO terms (including arbitration) materially altered the contract, so arbitration was not binding Jedson relied on Purchase Order terms to assert arbitration right Court declined to decide on the contract-formation question on appeal as interlocutory; result would be same (no stay), so cross-appeal not entertained

Key Cases Cited

  • Harsco Corp. v. Crane Carrier Co., 122 Ohio App.3d 406, 701 N.E.2d 1040 (Ohio Ct. App.) (courts hesitate to infer waiver of arbitration; distinguishes mutual arbitration agreements from unilateral-option clauses)
  • Morris v. Morris, 189 Ohio App.3d 608, 2010-Ohio-4750, 939 N.E.2d 928 (Ohio Ct. App.) (party asserting waiver bears burden; requests inconsistent with arbitration may support waiver)
Read the full case

Case Details

Case Name: John A. Becker Co. v. Jedson Eng'g, Inc.
Court Name: Ohio Court of Appeals
Date Published: Sep 28, 2018
Citation: 121 N.E.3d 788
Docket Number: 27891
Court Abbreviation: Ohio Ct. App.