History
  • No items yet
midpage
Jmr Construction Corp. v. United States
2014 U.S. Claims LEXIS 633
Fed. Cl.
2014
Read the full case

Background

  • JMR Construction contracted with the U.S. Army Corps of Engineers on June 26, 2007 to build an aircraft maintenance facility at Nellis AFB with a 420‑day performance period; final work was completed September 4, 2009.
  • Project suffered multiple delays (design issues, base scheduling conflicts, faulty structural steel, and later a custom permanent power converter and Room 109 lighting), resulting in four contract modifications and an extended completion date.
  • Key disputed periods for damages are January 16–February 3, 2009 and February 4–September 4, 2009; JMR removed its job trailer on February 3 and performed limited on‑site work afterward (four days) and some off‑site administrative work.
  • JMR submitted Requests for Equitable Adjustment and later appealed a contracting officer’s denial under the Contract Disputes Act, seeking field overhead, home (unabsorbed) office overhead (Eichleay) damages, and related bond/fee, painting, scheduling, and consulting costs totaling about $428,261.44.
  • The government moved for partial summary judgment seeking dismissal of field overhead for Feb 4–Sept 4, all home office overhead damages for Feb 4–Sept 4, and related fee/bond amounts; JMR conceded some categories (painting, scheduling, consulting and certain home office periods) but contested others.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Entitlement to field (jobsite) overhead for Feb 4–Sept 4, 2009 JMR says it performed field work after Feb 3 (Quality Assurance Reports) and incurred jobsite overhead during the delay. US argues JMR removed its job trailer Feb 3 and did not occupy the field; post‑Feb 3 on‑site activity was minimal so no field presence. Denied summary judgment for defendant — QA reports show six days of field work after Feb 3, creating a factual dispute.
Entitlement to home (unabsorbed) office overhead for Jan 16–Feb 3, 2009 (Eichleay standby elements) JMR contends work during this period was minor/punchlist/changed work and that most contract work was suspended, satisfying Eichleay standby. US contends significant on‑site work occurred (avg. ~10 hrs/day) so work was not suspended and standby cannot be shown. Denied summary judgment for defendant — material factual dispute as to whether work was sufficiently suspended to satisfy Eichleay standby.
Entitlement to home (unabsorbed) office overhead for Feb 4–Sept 4, 2009 (Eichleay standby elements) JMR argues delays (especially the custom power converter) were indefinite and it was required to remain on standby. US argues delays were knowable/not indefinite, remaining tasks were non‑time sensitive (temporary measures in place), and JMR was not required to return at "full speed and immediately," so standby fails. Granted summary judgment for defendant — JMR cannot show it was required to return at full speed and immediately (stopgap measures and lack of time‑sensitive tasks).
Fee and bond/insurance damages derived from overhead reductions JMR seeks these as percentages tied to overhead claims. US asks proportional reduction if overhead is disallowed. Denied summary judgment for defendant — relationship between these items and overhead not sufficiently defined on the record; factual development required.

Key Cases Cited

  • E.R. Mitchell Constr. Co. v. Danzig, 175 F.3d 1369 (Fed. Cir.) (Eichleay formula governs recovery of unabsorbed home office overhead)
  • Nicon, Inc. v. United States, 331 F.3d 878 (Fed. Cir.) (Eichleay prerequisites and burden shifting on replacement work)
  • P.J. Dick Inc. v. Principi, 324 F.3d 1364 (Fed. Cir.) (three‑part Eichleay standby test explained)
  • Interstate Gen. Gov't Contractors, Inc. v. West, 12 F.3d 1053 (Fed. Cir.) (idleness not required to show standby; minor tasks do not necessarily defeat standby)
  • Cmty. Heating & Plumbing Co., Inc. v. Kelso, 987 F.2d 1575 (Fed. Cir.) (field/jobsite overhead is recoverable)
  • Mech–Con Corp. v. West, 61 F.3d 883 (Fed. Cir.) (requirement that contractor be required to resume with urgency for standby)
  • Altmayer v. Johnson, 79 F.3d 1129 (Fed. Cir.) (home office overhead is indirect and allocable; cited on Eichleay principles)
Read the full case

Case Details

Case Name: Jmr Construction Corp. v. United States
Court Name: United States Court of Federal Claims
Date Published: Jul 14, 2014
Citation: 2014 U.S. Claims LEXIS 633
Docket Number: 1:11-cv-00187-LB
Court Abbreviation: Fed. Cl.