History
  • No items yet
midpage
Jay Miller & Sundown, Inc. D/B/A Sundown Construction (Appellant/Cross Appellee) v. Camp, Dresser & McKee, Inc. D/B/A CDM (Appellee/Cross Appellant)
2012 Tex. App. LEXIS 6776
Tex. App.
2012
Read the full case

Background

  • CDM, an engineering firm, designed and assisted with a water-project for the City of Del Rio; Sundown was the general contractor.
  • Sundown filed suit in 2007 for breach of contract and prompts, later adding tort claims related to City delays and water pumping issues.
  • CDM was designated a responsible third party under chapter 33, and Sundown joined CDM within 60 days of designation.
  • Sundown amended to add tort claims against CDM; the City later settled and nonsuited.
  • CDM sought dismissal under Chapter 150 (certificate of merit) and moved for summary judgment arguing the claim was time-barred.
  • The trial court granted summary judgment on the limitations issue but denied dismissal under Chapter 150; Sundown appealed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether §33.004(e) revives a limitations-barred claim Sun argues designation and timely joinder prevent limitations bar CDM contends §33.004(e) cannot revive the claim depending on the nature of alleged harm Yes; Sundown prevailed that §33.004(e) revives the claim.
Whether CDM was properly designated as a responsible third party Sundown correctly designated CDM within 60 days of designation CDM challenges designation validity under §33.004 CDM designation proper; limitations not a bar.
Whether a certificate of merit was required under Chapter 150 for Sundown’s claims Second 2005 Act applied retroactively to firms? Certificate required for actions accruing after 2005; Sundown’s accrued before Certificate of merit not required; pre-2005 accrual applies.
Whether the 2009 amendments to Chapter 150 apply to Sundown’s action against CDM 2009 Act governs changes; retroactive to pre-2005 actions? 2009 Act applies only to actions commenced after its effective date 2009 amendments do not apply; action governed by prior law; court erred in summary judgment.

Key Cases Cited

  • Flack v. Hanke, 334 S.W.3d 251 (Tex. App.—San Antonio 2010) (revival of limitations under §33.004(e) allowed)
  • Galbraith Eng’g Consultants, Inc. v. Pochucha, 290 S.W.3d 863 (Tex. 2009) (statutory interpretation of Chapter 33; designation of RTP)
  • S & P Consulting Eng’rs, PLLC v. Baker, 334 S.W.3d 390 (Tex. App.—Austin 2011) (discussed 2009 Act effective date and action commencement)
  • Raba-Kistner Consultants, Inc., 311 S.W.3d 584 (Tex. App.—El Paso 2010) (Chapter 150 applicability to design professionals)
  • Entergy Gulf States, Inc. v. Summers, 282 S.W.3d 433 (Tex. 2009) (statutory interpretation—de novo review standard)
Read the full case

Case Details

Case Name: Jay Miller & Sundown, Inc. D/B/A Sundown Construction (Appellant/Cross Appellee) v. Camp, Dresser & McKee, Inc. D/B/A CDM (Appellee/Cross Appellant)
Court Name: Court of Appeals of Texas
Date Published: Aug 15, 2012
Citation: 2012 Tex. App. LEXIS 6776
Docket Number: 04-11-00056-CV
Court Abbreviation: Tex. App.