History
  • No items yet
midpage
JAMES J. FORBES & FAY ANNETTE FORBES v. PRIME GENERAL CONTRACTORS, INC.
255 So. 3d 448
| Fla. Dist. Ct. App. | 2018
Read the full case

Background

  • Forbes (James and Fay) contracted with Prime General Contractors to renovate their home for $276,000 paid in five draws; Forbes paid the first two draws ($138,000) and $6,000 for updated architectural plans.
  • Prime demanded more money mid-job (claimed material costs rose; presented change order asking for ~ $550,000 total) and walked off when Forbes refused to sign; home left uninhabitable.
  • Forbes rented for five months while soliciting replacement contractors (none would finish the job), then bought a new house and let the unfinished home go into foreclosure, losing about $45,000 equity they had at contracting.
  • Forbes sued for breach of contract seeking restitution to precontract position (return of payments, architectural plan costs, lost equity) plus rent and other expenses; Prime defended partly on mitigation and contested damages.
  • After a bench trial the court found Prime materially breached but awarded only $5,600 rent, rejecting Forbes’s requested restitution and finding Forbes failed to mitigate; Forbes appealed.

Issues

Issue Forbes's Argument Prime's Argument Held
Proper measure of damages after a material breach Forbes elected to treat breach as total and sought rescissory damages to restore precontract position (return of payments, plan costs, lost equity) Contract should be treated as partially performed; damages measured by benefit-of-the-bargain (cost to complete or diminution in value) Court reversed: trial court used wrong measure; Forbes validly elected rescissory remedy and is entitled to be restored to precontract position
Burden/evidence for benefit-of-the-bargain remedy Forbes did not pursue benefit-of-the-bargain; thus lack of proof on completion costs/value is irrelevant Trial court relied on Forbes's failure to prove market-value/completion-cost evidence to deny benefit-of-the-bargain damages Court held trial court misapplied this standard because Forbes sought rescission, not benefit-of-the-bargain
Mitigation (avoidable-consequences) defense Forbes argued they tried reasonably to mitigate (sought other contractors, rented while searching, eventually bought new house when no contractor available) Prime argued Forbes failed to mitigate and made financial choices that increased damages Court held there was no competent substantial evidence Forbes could have avoided damages with reasonable efforts; mitigation defense failed
Remedy on remand Forbes seeks full rescissory damages restoring precontract position Prime seeks affirmation of limited award and mitigation finding Court remanded for entry of amended judgment awarding damages necessary to restore Forbes to precontract position; affirmed remainder of judgment

Key Cases Cited

  • Tubby’s Customs, Inc. v. Euler, 225 So. 3d 405 (Fla. 2d DCA 2017) (distinguishes rescissory vs. benefit-of-the-bargain remedies)
  • Hyman v. Cohen, 73 So. 2d 393 (Fla. 1954) (nonbreaching party may treat material breach as total and elect rescissory remedy)
  • Rector v. Larson’s Marine, Inc., 479 So. 2d 783 (Fla. 2d DCA 1985) (nonbreaching party may suspend performance and elect remedies)
  • City of Miami Beach v. Carner, 579 So. 2d 248 (Fla. 3d DCA 1991) (explains election between rescission and affirmance with benefit-of-the-bargain damages)
  • McCray v. Murray, 423 So. 2d 559 (Fla. 1st DCA 1982) (permitting rescissory relief and explaining inconsistency between remedies)
  • Grossman Holdings Ltd. v. Hourihan, 414 So. 2d 1037 (Fla. 1982) (adopts Restatement approach to construction-contract damages for completion or diminution in value)
  • Sys. Components Corp. v. Florida Dept. of Transp., 14 So. 3d 967 (Fla. 2009) (avoidance-of-consequences doctrine does not require plaintiff to undertake Herculean efforts)
  • Graybar Elec. Co. v. Stratton of Fla., Inc., 509 So. 2d 1133 (Fla. 2d DCA 1987) (reversing application of avoidable-consequences where evidence was insufficient)
Read the full case

Case Details

Case Name: JAMES J. FORBES & FAY ANNETTE FORBES v. PRIME GENERAL CONTRACTORS, INC.
Court Name: District Court of Appeal of Florida
Date Published: Sep 7, 2018
Citation: 255 So. 3d 448
Docket Number: 17-0353
Court Abbreviation: Fla. Dist. Ct. App.