History
  • No items yet
midpage
650 S.W.3d 392
Tex.
2022
Read the full case

Background:

  • Westlake contracted James (with Primoris as guarantor) for construction at a chlor-alkali plant; work was issued by work orders and Westlake could hire other contractors.
  • Contract required contractor safety, gave Westlake an intervention right (Section 17.2), and a separate termination-for-default mechanism (Section 21.3) that triggered recovery of any excess completion costs—but Section 21.3 required three written notices and Section 9.1 required all contract notices be in writing.
  • After a fatal December 28, 2012 workplace accident and additional safety incidents, Westlake shifted remaining mechanical work to Turner; Westlake never sent written termination notices required by Section 21.3.
  • Westlake sued James for excess costs; a jury found breaches by both sides and awarded damages and attorney’s fees to Westlake and attorney’s-fee damages to James on a consequential-damages theory. The court of appeals upheld most awards, applying substantial-compliance to the notice requirements.
  • The Texas Supreme Court held (1) substantial compliance ordinarily suffices for notice conditions, but a contract-mandated written notice cannot be satisfied without some writing; (2) Westlake failed to provide the required written notices and therefore may not recover under Section 21.3; (3) Westlake also cannot recover those same costs under Section 17.2; (4) Westlake’s indemnity recovery under Section 19.1 survives; and (5) Section 26 is a waiver of consequential damages, not a covenant not to sue, so James’s counterclaim fails. The Court remanded for reconsideration of attorney’s fees.

Issues:

Issue Plaintiff's Argument (Westlake) Defendant's Argument (James) Held
1. Standard for satisfying contractual notice conditions (strict vs substantial compliance) Substantial compliance should suffice to satisfy notice conditions Strict compliance required (especially for conditions precedent in construction contracts) Substantial compliance is the default rule, but where the contract requires written notice, some writing is necessary; oral notice cannot satisfy a written-notice condition absent waiver.
2. Sufficiency of the notices actually provided (were they in writing and adequate?) The parties exchanged communications and Westlake substantially complied with Section 21.3 At least two of the three required notices were never given in writing, so Westlake failed the condition precedent Westlake did not provide the requisite writings for at least two notices and therefore failed to substantially comply as a matter of law; recovery under Section 21.3 cannot stand.
3. Whether Section 17.2 (intervention) allows recovery of excess completion costs Section 17.2 authorized Westlake to intervene and recover the same excess costs Section 17.2 authorizes remedial intervention/costs during performance but does not authorize termination-and-cost-shifting that Section 21.3 governs Section 17.2 does not supplant Section 21.3; it cannot be read to permit recovery of termination-for-default completion costs and thus does not provide an independent basis to recover those costs.
4. Whether Section 26 is a waiver of consequential damages or a covenant not to sue Section 26 is a waiver of liability for consequential damages only; it does not bar bringing claims It is a covenant not to sue—so bringing a suit seeking consequential damages breaches the contract Section 26 is a waiver of consequential damages, not a covenant not to sue; Westlake’s pursuit of disputed damages did not, by itself, breach Section 26, so James’s counterclaim fails.

Key Cases Cited

  • Solar Applications Eng’g, Inc. v. T.A. Operating Corp., 327 S.W.3d 104 (Tex. 2010) (defines condition precedent and legal effect of unmet conditions)
  • Prodigy Commc’ns Corp. v. Agric. Excess & Surplus Ins. Co., 288 S.W.3d 374 (Tex. 2009) (applies notice–prejudice principle in insurance context)
  • PAJ, Inc. v. Hanover Ins. Co., 243 S.W.3d 630 (Tex. 2008) (reduced consequences for minor notice deviations when insurer not prejudiced)
  • Shaller v. Commercial Standard Ins. Co., 309 S.W.2d 59 (Tex. 1958) (holding oral notice insufficient where written notice is contractually required)
  • Emerald Forest Util. Dist. v. Simonsen Constr. Co., 679 S.W.2d 51 (Tex. App.—Houston [14th Dist.] 1984) (oral notice did not satisfy contractually required written notice)
  • S. Tex. Elec. Co-op v. Dresser–Rand Co., 575 F.3d 504 (5th Cir. 2009) (discusses substantial-compliance doctrine applied to contractual notice provisions)
  • J.M. Davidson, Inc. v. Webster, 128 S.W.3d 223 (Tex. 2003) (contract construction principles; give effect to whole contract)
  • Berry v. McAdams, 55 S.W. 1112 (Tex. 1900) (explains purpose and utility of written-notice statutory requirements)
Read the full case

Case Details

Case Name: James Construction Group, LLC and Primoris Services Corporation v. Westlake Chemical Corporation
Court Name: Texas Supreme Court
Date Published: May 20, 2022
Citations: 650 S.W.3d 392; 20-0079
Docket Number: 20-0079
Court Abbreviation: Tex.
Log In
    James Construction Group, LLC and Primoris Services Corporation v. Westlake Chemical Corporation, 650 S.W.3d 392