History
  • No items yet
midpage
J. Wm. Foley, Inc. v. United Illuminating Co.
158 Conn.App. 27
Conn. App. Ct.
2015
Read the full case

Background

  • Foley bid $43,344,000 to perform trenching, duct banks, and splice chambers; contract dated Sept 29, 2006; Article 6 governs change orders and a ten‑business‑day notice for delay claims; unknown site conditions entitle Foley to compensation for delays; project involved 69 miles of line with a 6‑mile trench through congested areas; construction delays stemmed from unknown utilities, soil conditions, and Foley/Manafort/Rizzo performance issues; August 2007 United letter modified change‑order process distinguishing direct costs/crew delays from critical path delays and did not waive ten‑day rule; Foley submitted its first essential critical path delay analysis in 2012, well after project completion; trial court found Foley irrevocably waived its delay claim and entered judgment for United on the delay claim; Foley received only three successful change orders and denied prejudgment and retainage interest, CUTPA, negligence, and leave to amend were denied.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the ten‑day rule applies to critical path delay claims Foley argues ten‑day rule may not apply to CP delays United contends CP delay claims fall within ten‑day rule Yes, ten‑day rule applies to CP delays
Whether United waived the ten‑day requirement Foley asserts August 2007 letter waived notice United did not intend to waive rights; letter preserved rights No waiver; ten‑day rule remains in effect
Whether Foley is entitled to a 10% markup on settlement payments Markup provision covers settlements Markup applies to change orders only; settlements not covered Foley not entitled to markup on settlement payments
Whether prejudgment interest under § 37‑3a and retainage interest under § 42‑158j should be awarded Foley seeks prejudgment and retainage interest Court is discretionarily justified to withhold interest No prejudgment or retainage interest awarded
Whether negligence and CUTPA claims were properly rejected and leave to amend denied Foley contends additional tort/CUTPA claims exist Claims lack duty/standard of care and fail relation back; amendment denied Negligence and CUTPA claims rejected; leave to amend denied

Key Cases Cited

  • Warning Lights & Scaffold Service, Inc. v. O&G Indus., Inc., 102 Conn. App. 267 (Conn. App. 2007) (damages proof and breach of contract standards; appellate review)
  • Bristol v. Ocean State Job Lot Stores of Connecticut, Inc., 284 Conn. 1 (2007) (contract interpretation; give effect to all provisions)
  • Texaco, Inc. v. Rogow, 150 Conn. 401 (1963) (reading contract terms by implication not allowed unless necessary)
  • Sherman v. Ronco, 294 Conn. 548 (2010) (relation back doctrine; new and different factual situations not relate back)
  • Deming v. Nationwide Mut. Ins. Co., 279 Conn. 745 (2006) (relation back and statute of limitations considerations)
  • Grenier v. Commissioner of Transportation, 306 Conn. 523 (2012) (amendment timing and relation to prior pleading; discretion)
  • Ruiz v. Gatling, 73 Conn. App. 574 (2002) (credibility findings; appellate deference to trial court)
  • Centimark Corp. v. Village Manor Assocs. Ltd. P’ship, 113 Conn. App. 509 (2009) (CUTPA review; standard of review and evidence sufficiency)
Read the full case

Case Details

Case Name: J. Wm. Foley, Inc. v. United Illuminating Co.
Court Name: Connecticut Appellate Court
Date Published: Jun 23, 2015
Citation: 158 Conn.App. 27
Docket Number: AC36194
Court Abbreviation: Conn. App. Ct.