History
  • No items yet
midpage
Islands Mechanical Contractor, Inc.
ASBCA No. 59655
| A.S.B.C.A. | Apr 13, 2017
Read the full case

Background

  • The Navy awarded Islands Mechanical Contractor, Inc. (IMC) a firm-fixed-price contract in 2006 to repair a wastewater treatment system at Naval Station Guantanamo Bay.
  • IMC encountered unforeseen site conditions and alleges defective plans/specifications and nonresponsive RFIs from NAVFAC, causing delays and equipment placed on standby since April 3, 2009.
  • IMC submitted proposals and revisions seeking payment for standby equipment, home office overhead, and a $373,121.78 proposal to complete the contract; NAVFAC did not accept the completion proposal or fully resolve RFIs.
  • IMC certified multiple claims (original, revised, second revised). The operative (second revised) certified claim sought specific dollar amounts for standby equipment and overhead and also included the $373,121.78 completion proposal and requested an extension of time.
  • IMC filed an appeal to the ASBCA after a deemed denial. The government moved to dismiss for lack of jurisdiction, arguing IMC failed to present a cognizable claim seeking a sum certain and sought relief (specific performance/injunctive relief) beyond Board authority.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the Board has jurisdiction under the CDA IMC says it presented a certified claim including $1,974,378.88 in sum certain (standby + overhead) and seeks relief; therefore appeal is cognizable. Government says the certified claim includes a proposal for work ($373,121.78) and seeks injunctive/specific relief; thus the claim is not a sum certain as a matter of right and is not cognizable. Dismissed for lack of jurisdiction: the claim did not present an overall sum certain as required.
Whether a proposal for additional work satisfies the CDA sum-certain requirement IMC contends the completion proposal was part of its claim or was included inadvertently and should be severed. Government contends a proposal is not a claim as of right and defeats the sum-certain requirement; severing is improper because claims must be presented to contracting officer as certified. Proposal for additional work ($373,121.78) is not a sum-certain demand; it prevents the overall claim from qualifying.
Whether the Board can order injunctive relief or direct contract modification (e.g., acceptance without warranties, direction to proceed, contract modification, time extension) IMC requests directions, contract modification, acceptance of equipment without warranties, replacement costs, and time extension. Government argues Board lacks authority to grant injunctive or specific-performance relief or to order contracting officer to modify contract beyond CDA remedies. Board lacks jurisdiction to grant injunctive/specific-performance relief or to order contracting officer to modify the contract; such claims are outside Board authority.
Whether partial sum-certain components suffice when other parts of the claim are not sum certain IMC argues the sum-certain portions (standby/equipment/overhead) should be considered and the rest ignored. Government asserts the entire claim must be a sum certain; Board should not sever and entertain only parts. Board will not entertain the sum-certain portion while discarding the remainder; the entire claim must be sum certain.

Key Cases Cited

  • Reflectone, Inc. v. Dalton, 60 F.3d 1572 (Fed. Cir. 1995) (en banc) (a cognizable CDA claim must be a written demand seeking a sum certain as a matter of right)
  • Essex Electro Engineers, Inc. v. United States, 960 F.2d 1576 (Fed. Cir. 1992) (a proposal for future work is not a claim as a matter of right and does not satisfy sum-certain requirement)
Read the full case

Case Details

Case Name: Islands Mechanical Contractor, Inc.
Court Name: Armed Services Board of Contract Appeals
Date Published: Apr 13, 2017
Docket Number: ASBCA No. 59655
Court Abbreviation: A.S.B.C.A.