History
  • No items yet
midpage
163 Conn.App. 440
Conn. App. Ct.
2016
Read the full case

Background

  • Plaintiffs Paul and Lisa Ippolito contracted with Olympic Construction to repair storm water damage; the contract used AIA A133–2009 and incorporated A201–2007 General Conditions.
  • During repairs a subsequent storm prompted Paul Ippolito to terminate the contract before completion.
  • Olympic initiated arbitration seeking lost profits for work it could not complete due to the termination; the arbitrator awarded $46,448.19 to Olympic, finding the termination was without cause.
  • Plaintiffs sought to vacate the award in Superior Court, arguing the home improvement contract violated the Home Improvement Act (HIA) because (1) the cancellation notice was improperly located (HIA §20-429(a)(6) / HSSA §42-135a) and (2) the contract lacked fixed start and completion dates (HIA §20-429(a)(7)); the trial court confirmed the award.
  • On appeal plaintiffs argued the arbitration award violated clear public policy and manifested disregard of law; the Appellate Court affirmed the trial court, upholding the award.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Cancellation notice placement (HIA §20-429(a)(6) / HSSA §42-135a) Cancellation notice was "buried" in incorporated A201 pages 38–39 and not in immediate proximity to signature as HSSA requires, rendering contract unenforceable Notice was included by incorporation and referenced near signature; any deviation was minor/technical and did not deprive plaintiffs of notice Award did not violate public policy; incorporated notice gave substance of required notice and deviation was minor so enforcement is permissible
Start and completion dates (HIA §20-429(a)(7)) Contract lacked fixed calendar start/completion dates, so it is unenforceable Contract defines commencement and completion by contract provisions (e.g., notice to proceed, GMP acceptance) — dates can be readily deduced Arbitrator found start/completion dates ascertainable from contract; court bound by that factual finding and held statute was satisfied
Public-policy vacatur of arbitration award Enforcing a noncompliant HIA contract violates explicit, dominant public policy and requires vacatur HIA compliance need not be technically perfect; minor defects that do not deprive owners of notice do not implicate dominant public policy No well-defined dominant public policy was violated because deviations were minor and did not deprive plaintiffs of cancellation notice or required dates
Manifest disregard of law under §52-418(a)(4) Arbitrator recognized statutory requirements but ignored them when enforcing the contract Arbitrator made factual findings that deviations were minor or nonexistent; did not ignore clearly governing law Plaintiffs failed Garrity test: no obvious error, no showing arbitrator knowingly ignored clearly applicable law; award not vacated

Key Cases Cited

  • Economos v. Liljedahl Bros., Inc., 279 Conn. 300 (arbitral review limited; grounds for vacatur narrowly confined)
  • Burr Road Operating Co. II, LLC v. New England Health Care Employees Union, 316 Conn. 618 (two‑pronged test for public‑policy vacatur of arbitration awards)
  • AFSCME, Council 4, Local 1565 v. Dept. of Correction, 298 Conn. 824 (deference to arbitrator's factual findings when reviewing public‑policy challenge)
  • Wright Bros. Builders, Inc. v. Dowling, 247 Conn. 218 (HIA is remedial; requires compliance but not necessarily technically perfect adherence to every formality)
  • Garrity v. McCaskey, 223 Conn. 1 (adopts Second Circuit three‑part test for manifest disregard of law under §52‑418(a)(4))
Read the full case

Case Details

Case Name: Ippolito v. Olympic Construction, LLC
Court Name: Connecticut Appellate Court
Date Published: Mar 1, 2016
Citations: 163 Conn.App. 440; 136 A.3d 653; AC37437
Docket Number: AC37437
Court Abbreviation: Conn. App. Ct.
Log In
    Ippolito v. Olympic Construction, LLC, 163 Conn.App. 440