History
  • No items yet
midpage
International Alliance of Theatrical Stage Employee & Moving Picture Technicians, Artist, & Allied Crafts of the United States v. InSync Show Productions, Inc.
801 F.3d 1033
9th Cir.
2015
Read the full case

Background

  • IATSE and InSync entered a 2003–2007 collective bargaining agreement (CBA) that included (1) an "evergreen" term provision stating the CBA would continue "from year to year thereafter" and (2) an arbitration/grievance clause covering claims that the employer "has violated or is violating the provisions of th[e] Agreement."
  • Negotiations for a successor agreement occurred 2007–2009; InSync informed the union it would not renew and later said bargaining had reached impasse. InSync never signed a proposed 2008–2012 extension that mirrored the 2003–2007 terms.
  • IATSE filed a grievance in 2011 asserting InSync was bound by the evergreen clause and sought arbitration; InSync contended both statutory and contractual claims were time-barred.
  • In 2012 IATSE petitioned the district court under § 301 to compel arbitration; the district court ordered arbitration and "stayed" the case, declining to decide whether the evergreen clause had been canceled.
  • InSync appealed the order compelling arbitration; the Ninth Circuit considered whether the order was appealable and whether the dispute over contract duration was for the arbitrator or the court.

Issues

Issue Plaintiff's Argument (IATSE) Defendant's Argument (InSync) Held
Is the district court order compelling arbitration and staying the case appealable? The petition to compel arbitration was the only relief sought, so the order is final and appealable under § 1291 and Goodall‑Sanford. The FAA bars interlocutory appeals from stays under § 3 and § 16(b), so the stay renders the order nonappealable. The order was final and appealable: the stay had no legal/practical effect and the petition to compel was the only matter before the court, so § 1291 jurisdiction (Goodall‑Sanford) applies.
Does the dispute over whether the CBA expired (evergreen clause) belong to an arbitrator or the court? The arbitration clause covers grievances alleging employer violations of the Agreement, so an arbitrator should decide whether the evergreen clause kept the CBA in effect. The CBA expired and bargaining reached impasse; that threshold question should be decided by the court, not arbitrator. The question whether the CBA expired/was terminated is arbitrable. Under Interstate Distributor/Camping, the arbitration clause is broad enough to send the threshold expire/termination dispute to an arbitrator.
Is Litton controlling to require the court to decide expiration? N/A (IATSE relied on arbitrability presumption). Litton requires courts to resolve disputes about post‑expiration rights, so the court should decide. Litton is distinguishable—there the parties agreed the contract had expired. Here the parties dispute whether the evergreen clause kept the contract in effect; that is for the arbitrator.
Were timeliness or estoppel defenses resolved by the district court and appealable now? IATSE argued the grievance was timely after InSync’s unequivocal refusal; district court left timeliness/issues to arbitrator. InSync argued statutory and contractual time bars and estoppel; some defenses were raised late or not below. Timeliness under NLRA was rejected by InSync below but Ninth Circuit found IATSE filed within six months of unequivocal refusal; estoppel and other late‑raised defenses were waived and for the arbitrator where not preserved.

Key Cases Cited

  • Goodall‑Sanford v. United Textile Workers, 353 U.S. 550 (1957) (an order under § 301 compelling arbitration is a final decision under § 1291)
  • Green Tree Financial Corp.‑Alabama v. Randolph, 531 U.S. 79 (2000) (a district court order compelling arbitration and dismissing claims is a "final decision" under § 16(a)(3); a mere stay ordinarily is not appealable)
  • AT&T Technologies, Inc. v. Communications Workers, 475 U.S. 643 (1986) (arbitration is a matter of contract; courts decide arbitrability unless parties clearly and unmistakably delegate it)
  • Brotherhood of Teamsters v. Interstate Distributor Co., 832 F.2d 507 (9th Cir. 1987) (when parties dispute whether a CBA expired or was terminated, the first inquiry is whether the arbitration clause covers that dispute)
  • Camping Constr. Co. v. District Council of Iron Workers, 915 F.2d 1333 (9th Cir. 1990) (applies Interstate Distributor: customary broad arbitration clauses submit termination/repudiation disputes to arbitrators)
  • Litton Fin. Printing Div. v. NLRB, 501 U.S. 190 (1991) (addressed rights after an agreement's undisputed expiration; distinguishable where expiration is contested)
  • Granite Rock Co. v. Int’l Bhd. of Teamsters, 561 U.S. 287 (2010) (courts should order arbitration only where formation/enforceability of arbitration agreement is not in issue)
Read the full case

Case Details

Case Name: International Alliance of Theatrical Stage Employee & Moving Picture Technicians, Artist, & Allied Crafts of the United States v. InSync Show Productions, Inc.
Court Name: Court of Appeals for the Ninth Circuit
Date Published: Sep 4, 2015
Citation: 801 F.3d 1033
Docket Number: No. 12-17200
Court Abbreviation: 9th Cir.