History
  • No items yet
midpage
112 N.E.3d 1088
Ind. Ct. App.
2018
Read the full case

Background

  • Indiana (State) contracted with IBM under a ten-year, $1.3B Master Services Agreement (MSA) to modernize welfare eligibility (centralized/remote model) and set Policy Objectives tying contract interpretation to those objectives.
  • Rollout encountered performance problems, the Great Recession, and disasters; the State moved to a Hybrid ("Plan B") approach shifting some functions back to local offices; no executed change order for price.
  • The State terminated the MSA for cause (Oct. 2009). The State sued IBM for >$170M; IBM sued for >$52M; claims were consolidated and tried in a six-week bench trial.
  • Trial judge (Dreyer) found IBM had not materially breached and awarded IBM $49.5M (assignment and equipment fees). Appellate courts reversed on material breach but repeatedly affirmed IBM’s $49.5M award, remanding to compute damages and offsets.
  • On remand a subsequent trial judge (Welch) awarded the State ~$125M direct damages (mainly costs of implementing Hybrid) plus $3M consequential damages, offsetting IBM’s award; IBM challenges several aspects on appeal and seeks post-judgment interest on its $49.5M award.

Issues

Issue State (Plaintiff) Argument IBM (Defendant) Argument Held
Whether prior trial-court factual findings (Judge Dreyer) are law of the case on remand The supreme court accepted Dreyer's factual findings and only corrected the legal test, so Dreyer's findings remain binding Dreyer's findings were disturbed by appellate rulings; remand left open factual gaps (e.g., damages causation) for new findings Not law of the case as to damages; the supreme court decided material breach but left factual questions (e.g., Hybrid vs. Modernization damages) to be determined on remand
Whether costs from implementing Hybrid are recoverable as direct (reprocurement) damages under the MSA Hybrid is a different, more expensive system outside the MSA scope, so State cannot recover costs for a different system Hybrid fits within the MSA’s Policy Objectives and Schedule 3 (face-to-face/local access was contemplated); Hybrid remediation costs flowed naturally from IBM’s breach Costs to implement Hybrid are recoverable as Reprocurement Costs; the trial court’s award for those costs was affirmed
Whether IBM is entitled to post-judgment interest on the $49.5M award from the original 2012 judgment date The supreme court’s remand reversed liability and thus post-judgment interest should run only from the new judgment after offsets The assignment and equipment fees were affirmed on appeal; those portions of the original judgment survived and IBM is entitled to post-judgment interest from the original verdict date IBM is entitled to post-judgment interest on the affirmed $49.5M; remanded to calculate interest from the original verdict date
Whether the MSA’s direct-damages cap or new employee salaries limit State’s recovery (cross-appeal) The direct-damages cap should be the greater of $125M or the fees paid in the 12 months before the Claim; State asserts 12-month fees exceed $125M and seeks salaries for new staff as recoverable reprocurement costs The 12-month comparator uses the date of Claim (here May 13, 2010), so fees in that period were less than $125M; new-management and some new hires put State in a better position than pre-MSA and are not reasonable reprocurement costs Trial court properly capped direct damages at $125M; salaries for newly created post-termination management positions are not recoverable as Reprocurement Costs (would be a windfall)

Key Cases Cited

  • Greater Clark Cty. Sch. Corp. v. Myers, 493 N.E.2d 1267 (Ind. Ct. App. 1986) (discusses scope of remand and what issues remain for trial court on damages)
  • St. Margaret Mercy Healthcare Ctr., Inc. v. Ho, 663 N.E.2d 1220 (Ind. Ct. App. 1996) (law-of-the-case doctrine bars relitigation of issues decided on prior stages)
  • Am. Family Mut. Ins. Co. v. Federated Mut. Ins. Co., 800 N.E.2d 1015 (Ind. Ct. App. 2003) (explains limits of law-of-the-case when additional evidence on remand fills factual gaps)
  • Beam v. Wausau Ins. Co., 765 N.E.2d 524 (Ind. 2002) (post-judgment interest runs from original verdict unless judgment is reversed and remanded for new judgment)
  • Dana Companies, LLC v. Chaffee Rentals, 1 N.E.3d 738 (Ind. Ct. App. 2013) (measure of contract damages: losses that flow directly and naturally from breach)
Read the full case

Case Details

Case Name: Int'l Bus. Machs. Corp. v. State
Court Name: Indiana Court of Appeals
Date Published: Sep 28, 2018
Citations: 112 N.E.3d 1088; Court of Appeals Case No. 49A02-1709-PL-2006
Docket Number: Court of Appeals Case No. 49A02-1709-PL-2006
Court Abbreviation: Ind. Ct. App.
Log In