History
  • No items yet
midpage
Innovative Test Asset Solutions LLC v. United States
125 Fed. Cl. 201
Fed. Cl.
2016
Read the full case

Background

  • The Air Force issued an RFP (FA9101-13-R-0100) for Test Operations and Sustainment services at Arnold Engineering Development Complex; evaluation factors: Technical (four equal subfactors), Past Performance, and Cost-Price (technical + past performance "significantly more important" than cost).
  • Four offerors competed; award to National Aerospace Solutions, LLC in June 2015 after evaluations, with Innovative Test Asset Solutions, LLC receiving some technical risk weaknesses and a lower most-probable-cost adjustment in the cost-realism analysis.
  • Innovative Test protested at GAO, which sustained limited grounds: weaknesses in Qualified Personnel and Innovations & Efficiencies were cost risks and should have been considered in cost-price only; GAO recommended corrective action (reevaluation of technical risk for those subfactors).
  • The Air Force performed a limited reevaluation (new evaluators for the two GAO-sustained subfactors) and in November 2015 again awarded the contract to National Aerospace, upgrading Innovative Test’s technical risk ratings but retaining one qualitative weakness.
  • Innovative Test filed suit in the Court of Federal Claims seeking injunctive relief, alleging the Air Force breached the implied duty to fairly and honestly consider its proposal during reevaluation and raising multiple challenges to technical, cost-realism, and past-performance evaluations.
  • The Court denied Innovative Test’s motion and granted the government’s and intervenor’s cross-motions, holding the Air Force’s reevaluation and award decision were not arbitrary or capricious.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Did the Air Force breach implied duty to fairly and honestly consider Innovative Test’s proposal during the GAO-ordered reevaluation? Innovative Test: reevaluation was pretextual, aimed at preserving original award; source-selection docs and emails show intent to "beef up" rationale. Gov/National Aerospace: plaintiff alleges bad faith; record shows a limited, reasonable reevaluation consistent with GAO remedy and GAO already denied other grounds. Court: No breach. Although record gave rise to skepticism, reevaluation was rational, supported by evaluators’ analyses, and not pre-determined.
Were technical evaluations (Management Approach; Innovations & Efficiencies) arbitrary or improper? Innovative Test: Management Approach weakness (use of standard production units) was based on misreading and amounted to unstated criterion; Innovation #22 weakness duplicated cost concerns GAO already faulted. Gov: Technical rating and technical-risk are distinct; the Air Force reasonably identified legitimate technical-risk concerns and on reevaluation corrected cost-risk double-counting while retaining a narrowly tailored qualitative weakness. Court: Evaluations reasonable. Management Approach weakness rationally explained; reevaluated Innovations & Efficiencies weakness addressed non-cost qualitative risk and was permissible.
Was the cost-realism methodology (including Crystal Ball treatment of Day One savings) arbitrary or unfairly applied to Innovative Test? Innovative Test: evaluators lacked training/guidance; Crystal Ball inputs were subjective and led to improper most-probable-cost adjustments; Day One savings were double-counted and prejudicial. Gov: Cost-realism is within agency discretion; methodology and discussions were reasonable; offerors had opportunities to revise; differences in proposals justified different adjustments. Court: Agency cost-realism decisions fall within discretion; record shows considered analysis and discussions; no irrational assumptions or prejudice shown.
Was past-performance evaluation (credit to GP Strategies in National Aerospace JV) unreasonable and prejudicial? Innovative Test: GP Strategies performed a small share of prior OMIMS work yet received full credit, distorting past-performance comparison. Gov: Joint-venture/teamwork made isolating contributions difficult; agency reasonably treated integrated efforts as whole and assigned overall confidence ratings after reviewing many references. Court: While some support for Innovative Test’s view exists, past-performance rating was not so lacking in rational basis as to overturn award given the full record and other evaluation factors.

Key Cases Cited

  • Bannum, Inc. v. United States, 404 F.3d 1346 (Fed. Cir. 2005) (standards for judicial fact-finding from administrative record in bid protests)
  • Systems Application & Techs., Inc. v. United States, 691 F.3d 1374 (Fed. Cir. 2012) (existence of implied-in-fact contract to consider proposals fairly in procurement context)
  • Motor Vehicle Mfrs. Ass'n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (U.S. 1983) (arbitrary-and-capricious review requires rational connection between facts and agency choice)
  • Alabama Aircraft Indus., Inc.-Birmingham v. United States, 586 F.3d 1372 (Fed. Cir. 2009) (examples of agency action lacking rational basis)
  • PGBA, LLC v. United States, 389 F.3d 1219 (Fed. Cir. 2004) (uneven treatment in procurement can amount to abuse of agency discretion)
  • Galen Med. Assocs., Inc. v. United States, 369 F.3d 1324 (Fed. Cir. 2004) (deference to agency in cost-realism and best-value tradeoffs)
Read the full case

Case Details

Case Name: Innovative Test Asset Solutions LLC v. United States
Court Name: United States Court of Federal Claims
Date Published: Mar 7, 2016
Citation: 125 Fed. Cl. 201
Docket Number: 15-1290C
Court Abbreviation: Fed. Cl.