201 A.3d 373
Vt.2018Background
- LK Holdings filed a CPG application on December 9, 2016 for a 500 kW group net‑metered solar project in Whiting, VT and certified that adjoining landowners had been notified, but in fact provided no such notices at filing.
- The Public Utility Commission (PUC) sent a December 16, 2016 memorandum requesting supplemental municipal screening information and circulated that memorandum to the service list (including adjoiners).
- LK submitted supplemental materials and, belatedly, a notice to adjoining landowners on or about January 18, 2017 (notice dated Jan. 16/17). Missing appendices were also filed then.
- Intervenors moved to dismiss the application as incomplete for failure to notify adjoining landowners and for missing materials; PUC dismissed the petition on May 22, 2017 as incomplete when filed (Dec. 9, 2016) and denied reconsideration.
- The timing was outcome‑determinative because Act 99 revised the net‑metering rule effective Jan. 1, 2017; only CPG applications that were complete before that date could be reviewed under the pre‑2017 rule (under which LK’s project could qualify).
Issues
| Issue | Plaintiff's Argument (LK) | Defendant's Argument (PUC / Intervenors) | Held |
|---|---|---|---|
| Whether the Dec. 9, 2016 application was "complete" despite no adjoiner notice | Application contained all substantive materials and thus was substantially complete and entitled to pre‑2017 rule treatment | Notice to adjoining landowners was a required part of the application; total failure to notify makes the filing incomplete | PUC: application incomplete when filed; Court affirmed |
| Whether LK’s Jan. 18, 2017 curative notice should relate back to Dec. 9, 2016 filing | Curative filing should relate back, preserving pre‑2017 status | Rule 2.208 bars relation back; cure date is the date last defect removed | PUC: cure did not relate back; Court affirmed |
| Whether dismissal was an excessive remedy for the notice defect | PUC should have stayed proceedings and allowed cure or intervenor participation | Timing was critical because rule change took effect Jan. 1, 2017; dismissal is consistent with precedent | PUC acted within discretion; dismissal affirmed |
| Whether the PUC could apply the revised net‑metering program via order before formal rule adoption | The August 2016 order was ineffective absent formal rulemaking; due process required formal rulemaking | Act 99 expressly authorized temporary adoption by order if final rules were not yet promulgated; robust notice and public process occurred | PUC permissibly relied on its interim order; Court affirmed |
Key Cases Cited
- Smith v. Winhall Planning Comm'n, 436 A.2d 760 (Vt. 1981) (applicant’s rights vest only when a proper and complete application is filed)
- In re Jolley Assocs., 915 A.2d 282 (Vt. 2006) (completed zoning application filed before regulatory change can vest rights)
- Diel v. Dep't of Educ., 614 A.2d 1223 (Vt. 1992) (VAPA procedures generally provide sufficient process; due process may be satisfied by adequate notice and opportunity to be heard)
- Parker v. Gorczyk, 787 A.2d 494 (Vt. 2001) (legislature may establish procedures for agency policy; more specific statute controls over general statutes)
- In re Ross, 557 A.2d 490 (Vt. 1989) (incomplete application cannot establish vested rights under pre‑existing law)
