In re Ohio Power Co.
40 N.E.3d 1060
Ohio2015Background
- PUCO approved a phase-in recovery rider (PIRR) to let Ohio Power recover fuel costs deferred under its first electric-security plan (ESP) and allowed carrying charges on those deferred costs through 2018.
- The ESP Order (2009) set the carrying-charge rate at Ohio Power’s WACC (11.15%) for both the deferral (2009–2011) and recovery (2012–2018) periods; no party appealed that WACC determination.
- In the PIRR Order (2012), PUCO changed the carrying-charge rate prospectively for the recovery period to Ohio Power’s long-term cost-of-debt (5.34%), decreasing carrying-charge recovery by about $130 million.
- Ohio Power appealed, arguing (among other things) that PUCO’s post-ESP modification deprived it of the statutory right to withdraw a modified ESP under R.C. 4928.143(C)(2)(a); IEU cross-appealed, arguing PUCO should have reduced the deferred balance for accumulated deferred income taxes (ADIT).
- The Supreme Court of Ohio held PUCO’s post-expiration modification violated R.C. 4928.143(C)(2)(a) because it eliminated Ohio Power’s ability to withdraw a modified ESP, and therefore reversed the PIRR adjustment to the carrying-charge rate; IEU’s ADIT claim was barred by collateral estoppel.
Issues
| Issue | Plaintiff's Argument (Ohio Power) | Defendant's Argument (PUCO / IEU) | Held |
|---|---|---|---|
| Whether res judicata/collateral estoppel barred PUCO from modifying the carrying-charge rate set in the ESP Order | Res judicata/issue preclusion prevents PUCO from changing a final adjudication, divesting PUCO of authority to modify the ESP term | PUCO retains jurisdiction to modify prior orders; res judicata is an affirmative defense and does not deprive PUCO of jurisdiction | Res judicata argument rejected — no bar to PUCO jurisdiction to revisit order |
| Whether PUCO’s post-expiration change to the carrying-charge rate deprived Ohio Power of the right to withdraw a modified ESP under R.C. 4928.143(C)(2)(a) | Modification occurred after ESP expired, so Ohio Power could not exercise statutory withdrawal right; PUCO therefore violated the statute | PUCO argued the withdrawal provision applies only to orders that modify and approve an ESP application within the ESP proceeding, not later recovery proceedings | Court held PUCO’s modification violated R.C. 4928.143(C)(2)(a); reversed the rate change and remanded to reinstate WACC |
| Whether PUCO permissibly relied on its ongoing supervision/jurisdiction and precedent (including In re Columbus S. Power) to justify the change | (implicit) PUCO’s supervisory power allowed prospective modification of recovery mechanics | PUCO asserted broad supervisory authority and cited precedent justifying modifications to phase-in terms | Court held supervisory authority cannot be used to contravene statutory withdrawal right; cited distinction from cited precedent |
| Whether IEU’s claim that PUCO should reduce deferred balance for ADIT is reviewable | IEU argued ADIT yields cost-free capital and should reduce deferred balance and carrying charges | PUCO refused the ADIT reduction; argued prior ESP decision already addressed ADIT | Court held IEU’s ADIT challenge barred by collateral estoppel because issue was litigated in the first ESP case and IEU did not preserve it there |
Key Cases Cited
- Constellation NewEnergy, Inc. v. Pub. Util. Comm., 104 Ohio St.3d 530, 820 N.E.2d 885 (2004) (standard for reversing PUCO orders)
- Monongahela Power Co. v. Pub. Util. Comm., 104 Ohio St.3d 571, 820 N.E.2d 921 (2004) (deference on fact issues; appellant bears burden to show order is against manifest weight)
- Consumers’ Counsel v. Pub. Util. Comm., 58 Ohio St.2d 108, 388 N.E.2d 1370 (1979) (agency expertise in statute interpretation and limits on modifying prior orders)
- Cleveland Elec. Illuminating Co. v. Pub. Util. Comm., 42 Ohio St.2d 403, 330 N.E.2d 1 (1975) (agency should respect its own precedents; predictability)
- Util. Serv. Partners, Inc. v. Pub. Util. Comm., 124 Ohio St.3d 284, 921 N.E.2d 1038 (2009) (agency may change course if new course is permissible and explained)
- In re Application of Columbus S. Power Co., 128 Ohio St.3d 512, 947 N.E.2d 655 (2011) (prior ESP litigation; limits and standards for modifying ESP-related orders)
- Discount Cellular, Inc. v. Pub. Util. Comm., 112 Ohio St.3d 360, 859 N.E.2d 957 (2007) (PUCO is a creature of statute and has no authority beyond statutory powers)
- Fed. Communications Comm. v. Fox Television Stations, Inc., 556 U.S. 502 (2009) (an agency need not show new policy is superior; must show new policy is permissible and reasoned)
