IN RE NEWARK ENERGY CENTER PROPOSED AIR POLLUTION CONTROLOPERATING PERMIT MODIFICATION(NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION)
A-5794-14T1
| N.J. Super. Ct. App. Div. | Dec 1, 2017Background
- Newark Energy Center (NEC) operates a natural gas power plant in Newark; its 2012 Title V air permit allowed use of gray water and sulfuric acid (limited to 10.57 tpy).
- In 2014 NEC sought a significant permit modification to increase sulfuric acid use in its cooling tower (to treat gray water), asserting no increase in allowable sulfuric acid emissions.
- DEP published notice, held a public hearing, received comments (public safety, spill/notification concerns), and solicited EPA review; DEP proposed approval and later issued the modification in August 2015 after EPA raised no objection.
- The modification: raised permitted water tower chemical use (470 → 2267 tpy), included storage tank emissions in facility-wide sulfuric acid cap, added pH monitoring and recordkeeping, and retained the same emission caps.
- Appellants (Ironbound Community Corporation & NJ Environmental Justice Alliance) challenged the modification, arguing DEP should have required public emergency response/notification plans and detailed public reports under EPCRA, the Spill Act, and CAA §112(r) before approval.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether DEP had to obtain public emergency response/notification plans and detailed public reports (Spill Act/EPCRA) before issuing the Title V modification | Appellants: DEP must require compliance with Spill Act and EPCRA emergency planning/reporting prerequisites prior to permit approval | DEP/NEC: Spill Act and EPCRA impose separate requirements and enforcement mechanisms but do not condition issuance of air permits | Held: DEP acted within its authority; Spill Act and EPCRA obligations are separate and do not bar permit issuance when APCA/Title V requirements are met |
| Whether CAA §112(r)/CAPP rules required DEP to ensure completion of public emergency plans before permit modification | Appellants: CAA §112(r) (CAPP) was incorporated into 2012 permit and thus requires public emergency planning before modification | DEP/NEC: §112(r) applies only to listed regulated substances above threshold quantities; sulfuric acid is not a listed substance here, and §112(r) does not condition permitting decisions | Held: §112(r) does not apply to sulfuric acid here; even if it did, §112(r) does not link emergency planning compliance to Title V permit eligibility |
| Whether DEP’s factual determination that increased chemical use would not increase emissions was supported by the record | Appellants: Increased chemical use raises public-safety and emissions concerns and requires further proof | DEP/NEC: NEC provided calculations; DEP added monitoring/recordkeeping; EPA reviewed and raised no objections | Held: DEP’s determination is supported by substantial credible evidence; increased use did not raise permitted emissions and DEP imposed monitoring conditions |
| Whether DEP’s process complied with procedural requirements of Title V and APCA | Appellants: DEP failed to satisfy all statutory/regulatory prerequisites tied to emergency planning | DEP/NEC: DEP followed N.J.A.C. notice, hearing, public comment, and EPA review procedures | Held: DEP followed required notice, hearing, comment, and EPA review; process was not arbitrary or capricious |
Key Cases Cited
- In re Herrmann, 192 N.J. 19 (Appellate-review standard for administrative decisions)
- Lavezzi v. State, 219 N.J. 163 (deference to agency reasonableness)
- In re Young, 202 N.J. 50 (court should not substitute its judgment for agency)
- Barrick v. State, 218 N.J. 247 (substantial credible evidence standard and review framework)
- In re Carter, 191 N.J. 474 (factors for reviewing agency action applying legislative policy)
- Ocean Cty. Landfill Corp. v. USEPA, 631 F.3d 652 (Title V permitting framework; state implementation with EPA oversight)
- Util. Air Regulatory Grp. v. EPA, 134 S. Ct. 2427 (purpose of Title V as consolidating obligations rather than imposing substantive controls)
