History
  • No items yet
midpage
175 A.3d 1211
Vt.
2017
Read the full case

Background

  • GLC sought a certificate of public good (CPG) to build a 500 kW net‑metered solar array in New Haven; Board Rule 5.100 (2014) and 30 V.S.A. § 248/§ 219a procedures governed the application.
  • GLC provided a 45‑day advance notice and filed the formal application; the Town of New Haven submitted multiple rounds of comments arguing violations of § 248 criteria and town‑plan guidance limiting project size.
  • GLC amended its site plan (notably relocating access roads) and submitted a Fast Track Interconnection Analysis (FTA) from Green Mountain Power (GMP); the project failed Criterion 3 of the FTA but GMP later filed an addendum concluding further study unnecessary.
  • The Town filed substantial supplemental comments on September 17 asserting significant issues, including interconnection/system reliability concerns tied to the FTA Criterion 3 failure, and requested a technical hearing.
  • The Board granted the CPG without holding a technical hearing, deemed the Town’s September 17 comments untimely, and relied on GMP’s addendum and the Department of Public Service’s concurrence regarding interconnection.
  • The Vermont Supreme Court reversed and remanded: it held the Board erred in not considering the Town’s September 17 comments and remanded for at least a technical hearing on the interconnection/FTA issue and reconsideration of other unaddressed Town comments.

Issues

Issue Plaintiff's Argument (Town) Defendant's Argument (Board/GLC) Held
Whether the Board may decline to hold a hearing in a net‑metering case Rule 5.100 as applied here effectively eliminates hearings; Board lacks authority to dispense with hearings in particular cases Statute and Act 136 permit streamlined procedures and modified hearing requirements; rule is valid and within authority Board has authority to modify hearing requirements; streamlining allowed, but not carte blanche to ignore significant issues
Whether the Board erred in treating the Town’s Sept. 17 comments as untimely GLC’s application was not complete until GLC cured notice deficiency (Oct. 20), so Sept. 17 comments were timely Application was complete earlier; comments untimely under rule deadlines Court held the Board erred: Town’s Sept. 17 comments should have been considered because they were filed within the ten‑day window after the amended filing made the record complete
Whether the Board permissibly waived interconnection study requirements after FTA Criterion 3 failure Town: GMP’s decision to forgo a system impact study despite failing Criterion 3 raises a significant issue requiring a hearing, discovery, and independent Board fact‑finding GLC/GMP/Department: GMP addendum and Department engineering review show no system reliability issue; waiver appropriate Remanded: waiver of Board Rule 5.503(A) and decision to forgo further study were insufficiently explained; technical hearing required on interconnection/FTA Criterion 3 issue
Whether earlier Town filings (before Sept. 17) required a technical hearing Town: earlier 45‑day and initial comments raised significant § 248 issues necessitating hearing Board/GLC: earlier comments were largely generalized/speculative and GLC’s evidence addressed the concerns; no hearing required Court held earlier filings alone did not establish significant issues warranting a technical hearing, but Board must reconsider all Town comments on remand

Key Cases Cited

  • In re Rutland Renewable Energy, LLC, 147 A.3d 621 (Vt. 2016) (describing deferential standard of review for Public Service Board decisions)
  • In re UPC Vt. Wind, LLC, 969 A.2d 144 (Vt. 2009) (Board engages in policy‑making and is accorded substantial deference)
  • In re Green Mountain Power Corp., 648 A.2d 374 (Vt. 1994) (agency must explain its reasoning; expertise does not excuse conclusory determinations)
  • In re Cont’l Tel. Co. of Vt., Inc., 549 A.2d 639 (Vt. 1988) (Board must independently evaluate expert evidence and make factual findings)
Read the full case

Case Details

Case Name: In re New Haven GLC Solar, LLC
Court Name: Supreme Court of Vermont
Date Published: Aug 25, 2017
Citations: 175 A.3d 1211; 2017 VT 72; No. 16–125
Docket Number: No. 16–125
Court Abbreviation: Vt.
Log In
    In re New Haven GLC Solar, LLC, 175 A.3d 1211