History
  • No items yet
midpage
In re Korrow Real Estate, LLC Act 250 Permit Amendment Application (State of Vermont, Appellant)
187 A.3d 1125
Vt.
2018
Read the full case

Background

  • Korrow Real Estate built an ~8,000 sq. ft. barn and brought fill near the Dog River and Stony Brook in Northfield in 2012 without first obtaining an Act 250 permit; the parcel is a commercial "development" subject to Act 250.
  • ANR used its technical guidance (including a fluvial erosion hazard, FEH, assessment) to map an Act 250 "floodway" that included parts of the barn and fill, even though FEMA/NFIP maps did not.
  • The District 5 Commission, relying on ANR, found the project within the Act 250 floodway and on a river "shoreline," and ordered removal/relocation for noncompliance with Criteria 1(D) (floodway/floodway fringe) and 1(F) (shoreline).
  • The Environmental Division reversed: it rejected ANR’s floodway methodology, found the project outside the floodway, and concluded the project complied with Criteria 1(D) and 1(F), ordering issuance of an as-built Act 250 permit.
  • The Natural Resources Board appealed, arguing the Environmental Division failed to afford proper deference to ANR’s statutorily delegated expertise and methodologies; the Supreme Court affirmed in part, reversed in part, and remanded.

Issues

Issue Plaintiff's Argument (Korrow) Defendant's Argument (NRB/ANR) Held
Whether ANR’s FEH-based methodology properly defines the Act 250 "floodway" and whether the court should defer to ANR ANR methodology is incorrect; court’s own assessment shows project is outside floodway Legislature delegated floodway/floodway-fringe determinations to ANR; complex geomorphic methods are within ANR expertise and entitled to deference Court must defer to ANR on floodway definition absent arbitrary/capricious or due-process violation; ANR definition applied and project is within the floodway (but see compliance below)
Whether the project complies with Criterion 1(D) (development in floodway will not restrict/divert floodwaters or endanger others) Project’s location and evidence (slope, lack of historical flooding) show it will not restrict/divert floodwaters or endanger public/riparian owners If project is in ANR-defined floodway, it must meet Criterion 1(D) and ANR concerns about FEH impacts are significant Although within ANR floodway, record contains credible evidence supporting the Environmental Division’s factual findings that the project does not restrict/divert flows or endanger safety; Criterion 1(D) satisfied
Whether the project is on a "shoreline" (definition of "adjacent") and whether court should defer to NRB rule interpretation Project is not on a shoreline (court’s functional analysis) NRB Rule and statute define shoreline broadly; adjacency and potential impacts support shoreline finding Environmental Division’s factual findings that project is not on a shoreline are insufficient and inadequately define or apply "adjacent"; remand required for further findings and briefing on "adjacent"
If on shoreline, whether the project meets Criterion 1(F) including the statutory "of necessity" requirement Project complies with the four subcriteria (retain natural condition, access, screening, bank stabilization) If project is on shoreline, must also show it is "of necessity" located on the shoreline per statute and NRB rule Trial court failed to address the "of necessity" element and did not make adequate findings against the shoreline scope; remand for determination of shoreline status and, if applicable, "of necessity" and subcriteria compliance

Key Cases Cited

  • Plum Creek Me. Timberlands, LLC v. Vt. Dept. of Forests, Parks & Rec., 155 A.3d 694 (Vt. 2016) (courts must defer to agency interpretations of policy/methodology within agency expertise even in de novo hearings)
  • In re Woodford Packers, Inc., 830 A.2d 100 (Vt. 2003) (ANR has statutory authority to define Act 250 "floodway" and "floodway fringe"; agency methodology entitled to deference absent arbitrary/capricious application)
  • In re Zaremba Gr. Act 250 Permit, 127 A.3d 93 (Vt. 2015) (appellate review standard: factual findings reviewed for clear error; legal conclusions de novo)
  • In re Vill. Assocs. Act 250 Land Use Permit, 998 A.2d 712 (Vt. 2010) (clarifies standard of review and trial-court role in weighing evidence)
  • McShinsky v. Town of Colchester, 572 A.2d 916 (Vt. 1990) (courts must determine whether shoreline development is "of necessity" located on shoreline under Criterion 1(F))
Read the full case

Case Details

Case Name: In re Korrow Real Estate, LLC Act 250 Permit Amendment Application (State of Vermont, Appellant)
Court Name: Supreme Court of Vermont
Date Published: Apr 13, 2018
Citation: 187 A.3d 1125
Docket Number: 2017-133
Court Abbreviation: Vt.