187 A.3d 1138
Vt.2018Background
- Vermont Gas Systems (VGS) operated under an alternative regulation plan (ARP) and in 2011 established a System Expansion and Reliability Fund (SERF) to smooth rates for future expansion; Commission approved SERF with safeguards and required Commission authorization for any withdrawals.
- The Commission granted a Certificate of Public Good (CPG) in 2013 for a 41-mile, 12-inch pipeline (ANGP) to serve Addison County; projected ANGP costs rose significantly (to well over the original estimate).
- VGS later agreed (via an MOU with the Department of Public Service) to cap recoverable ANGP costs at $134 million (an effective ~$31 million disallowance) and to a reduced return on equity (ROE) of 8.5% for three years; the Commission incorporated that MOU into its 2017 ratemaking order and authorized a $5.5 million SERF withdrawal for FY2017.
- The Department’s expert recommended discrete disallowances (~$25M) plus a $10M global disallowance (total ~$35M) for imprudent early-project management; VGS contested those figures and AARP intervened, arguing for larger disallowances and for other relief.
- The Commission found VGS had engaged in some imprudent management early in the project but concluded the record did not support disallowing more than the effective $31M cap; it accepted the MOU, left non-gas rates unchanged, allowed the SERF withdrawal, and imposed the 8.5% ROE cap for three years.
Issues
| Issue | Plaintiff's Argument (AARP) | Defendant's Argument (VGS / Commission / Dept.) | Held |
|---|---|---|---|
| Sufficiency of findings on imprudent ANGP costs | Commission failed to make specific findings quantifying imprudent costs, preventing meaningful review | Record contained expert testimony and parties’ agreement; Commission’s conclusion that imprudent costs did not exceed $31M was adequate | Reversed and remanded: Commission must make further findings identifying amount/nature of imprudent costs so appellate review is possible |
| Adequacy of ROE reduction as penalty | 8.5% ROE cap for three years is unexplained and may be insufficient to offset imprudent costs allowed into rate base | ROE cap, together with $31M effective disallowance, reasonably addresses imprudence; ROE not challenged as excessive | Remanded contingent: if additional findings show ROE cap was used to offset undisclosed imprudent costs, Commission must explain/calibrate how ROE reduction compensates for those costs |
| Used-and-useful challenge to 12-inch vs. 10-inch pipeline | Additional cost of 12-inch line (vs. 10-inch) should be disallowed as not used and useful given no current plans for further expansion | CPG authorized 12-inch pipeline; no party in this ratemaking case presented evidence quantifying extra costs; long useful life supports inclusion | Affirmed: Commission’s finding that no party presented evidence on proper pipeline size is not clearly erroneous; costs retained in rate base for this period |
| Legality of SERF withdrawal / cross-subsidization | Allowing SERF withdrawal to smooth rates unlawfully subsidizes new customers by existing ones without explicit statutory authorization | SERF was approved under ARP with statutory notice/hearing criteria; some cross-subsidization is permissible and SERF withdrawals are subject to Commission oversight | Affirmed: Commission acted within discretion to allow $5.5M SERF withdrawal for FY2017 to smooth rates; not an unlawful subsidy here |
Key Cases Cited
- Citizens Utilities Co. v. Pub. Util. Comm’n, 171 Vt. 447, 769 A.2d 19 (Vt. 2000) (deferential review of Commission decisions and ratemaking expertise)
- In re Tariff Filing of Cent. Vt. Pub. Serv. Corp., 167 Vt. 626, 711 A.2d 1158 (Vt. 1998) (courts defer to Commission on ratemaking; role limited)
- In re Cent. Vt. Pub. Serv. Corp., 141 Vt. 284, 449 A.2d 904 (Vt. 1982) (recognizing Commission expertise in ratemaking decisions)
- In re Cont’l Tel. Co. of Vt., 150 Vt. 76, 549 A.2d 639 (Vt. 1988) (adequacy of administrative findings where board evaluated expert testimony)
- In re Consol. Rate Appeals of Green Mt. Power Corp., 142 Vt. 373, 455 A.2d 823 (Vt. 1983) (deference to Commission rate-setting choices directed at regulatory objectives)
- New England Tel. & Tel. Co. v. Pub. Serv. Bd., 115 Vt. 494, 66 A.2d 135 (Vt. 1949) (used-and-useful / property held for future use test)
- Latourneau v. Citizens Util. Co., 125 Vt. 38, 209 A.2d 307 (Vt. 1965) (useful-life and timing considerations for utility plant inclusion)
