History
  • No items yet
midpage
In re Individual 35W Bridge Litigation
806 N.W.2d 820
Minn.
2011
Read the full case

Background

  • Bridge collapse on August 1, 2007 at the I-35W crossing; Swift legal actions against URS, PCI, and Jacques alleging negligence, contract claims, and damages.
  • Jacobs’ predecessor Sverdrup designed the Bridge; Sverdrup later merged into Jacobs, making Jacobs a successor in interest.
  • State pursued compensation under 2008 statutes to reimburse survivor-claimants for paid benefits and expenses.
  • Compensation statutes authorize the State to recover payments from third parties that caused or contributed to the catastrophe; include § 3.7394, subd. 5(a).
  • Prior statute of repose (541.051, with earlier 1980 version) had extinguished related claims; 2007 amendments allegedly revived those claims; districts and appellate courts initially ruled for revival.
  • Court ultimately held that the 2007 amendments retroactively revive the State’s statutory reimbursement claim against Jacobs without violating due process or impairing contracts.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Retroactive revival of action for contractual indemnity State argues 2007 amendments revive extinguished contractual indemnity claim against Jacobs. Jacobs contends repose extinguished the claim; amendments do not revive. No revival for contractual indemnity under 541.051 prior version.
Retroactive revival of statutory reimbursement under 3.7394(5)(a) State asserts 3.7394(5)(a) revives the reimbursement claim against Jacobs. Jacobs argues no revival due to repose and constitutional limits. Notwithstanding clause retroactively revives statutory reimbursement against Jacobs.
Due process challenge to retroactive revival States rational basis supports revival; no due process violation. Jacobs asserts protected property interest in statute of repose; revival infringes that interest. Retroactive revival satisfies rational basis; no due process violation.
Contract impairment under Energy Reserves framework Reimbursement clause does not impair Sverdrup contract rights. Sverdrup contract immunity defenses could be affected. Not a substantial impairment under Energy Reserves test.
Pierringer releases and voluntary payments doctrine Notwithstanding clause negates Pierringer/voluntary payment limits. Releases should bar reimbursement. Not barred due to notwithstanding clause; State may seek reimbursement.

Key Cases Cited

  • Weston v. McWilliams & Assoc., 716 N.W.2d 634 (Minn. 2006) (statute of repose vs. limitations; substantial impairment analysis guidance)
  • Donaldson v. Chase Secs. Corp., 216 Minn. 269, 13 N.W.2d 1 (Minn. 1943) (statutes of limitations; retroactive application not a vested right)
  • Chase Sec. Corp. v. Donaldson, 325 U.S. 304 (U.S. 1945) (federal due process standards for retroactive legislation)
  • Sartori v. Hamischfeger Corp., 432 N.W.2d 448 (Minn. 1988) (identical due process analysis between state and federal constitutions)
  • Energy Reserves Group, Inc. v. Kan. Power & Light Co., 459 U.S. 400 (U.S. 1983) (three-part test for contract impairment due to legislation)
  • Kipp v. Johnson, 31 Minn. 360, 17 N.W. 957 (Minn. 1884) (no vested rights in exemption from forms of action; remedial statutes)
Read the full case

Case Details

Case Name: In re Individual 35W Bridge Litigation
Court Name: Supreme Court of Minnesota
Date Published: Nov 30, 2011
Citation: 806 N.W.2d 820
Docket Number: Nos. A10-0087, A10-0089, A10-0090, A10-0091
Court Abbreviation: Minn.