History
  • No items yet
midpage
In re Chaves A250 Permit Reconsider
195 Vt. 467
| Vt. | 2014
Read the full case

Background

  • Neighbors appeal an Environmental Division order granting an Act 250 permit for a sand and gravel quarry operated by Chaves Londonderry Gravel Pit, LLC; settlement changes to the project occurred before trial, including access point relocation, noise and traffic mitigations, and blasting plan; the site is on Route 100 in Londonderry with a long history of extraction; applicants initially believed operations were grandfathered; the Environmental Division held the modifications did not require remand and issued a permit with conditions; neighbors challenged four Act 250 criteria and condition 16, and the court remanded for clarification of condition 16.
  • Settlement changes included moving the quarry access to an existing north entrance, adding noise berms, limiting trips, scheduling drilling/blasting, and creating a blasting plan.
  • Trial was initially set for March 5, 2012; a settlement was adopted February 21, 2012; neighbors sought remand and continuance which were denied; evidence focused on traffic, noise, aesthetics, historic sites, and compliance with town and regional plans.
  • The Environmental Division reviewed four Act 250 criteria (traffic, aesthetics, extraction, conformity) and concluded conformance with conditions; the court applied deferential review and relied on expert testimony to assess noise and traffic impacts.
  • On appeal, the court affirmed but remanded for clarification of condition 16 regarding noise levels.
  • The project is subject to scrutiny under Quechee-based aesthetics analysis and local/ regional plan conformity, with emphasis on standards, existing traffic noise, and the enforceability of conditions.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether settlement changes required remand or continuance Hart objected to material changes needing remand Chaves Londonderry argued changes did not alter permit type or scale Remand not required; changes did not alter permit type or scope
Whether project complies with Act 250 criterion 8 (aesthetics) Neighbors claim noise and traffic create undue adverse aesthetic impact Court properly applied Quechee test with mitigating measures No undue adverse aesthetic impact; findings supported by credible evidence under Quechee test
Whether project complies with criterion 10 (conformity with town/regional plans) Plans contain unambiguous restrictions on historic resources Plans contain broad nonregulatory language; zoning allows quarry use Project conforms to town and regional plans; plans do not contain enforceable prohibitions
Whether condition 16 on noise is enforceable or vague Condition 16 relies on historical noise levels; not definite Condition provides noise constraint tied to prior levels Condition 16 vague; remand to revise to definite standard

Key Cases Cited

  • In re Sisters & Bros. Inv. Grp., LLP, 2009 VT 58 (Vt. 2009) (modifications to an application may be approved without remand if not a substantial change)
  • In re Torres, 154 Vt. 233 (Vt. 1990) (superior court authority limited to scope of original permit; remand required for substantial changes)
  • In re Rinkers, Inc., 2011 VT 78 (Vt. 2011) (Quechee framework; deferential review of aesthetics criteria)
  • Eastview at Middlebury, Inc., 2009 VT 98 (Vt. 2009) (Quechee analysis for aesthetic impacts and mitigation)
  • In re John A. Russell Corp., 2003 VT 93 (Vt. 2003) (conformity with plans; ambiguous plan language not enforceable)
  • In re JAM Golf, LLC, 2008 VT 110 (Vt. 2008) (planning/regulatory standards; vagueness problems when design to protect resources)
  • In re Molgano, 163 Vt. 25 (Vt. 1994) (zoning bylaw interpretation; implementational standards)
Read the full case

Case Details

Case Name: In re Chaves A250 Permit Reconsider
Court Name: Supreme Court of Vermont
Date Published: Jan 17, 2014
Citation: 195 Vt. 467
Docket Number: No. 13-069
Court Abbreviation: Vt.