History
  • No items yet
midpage
In re Application of Suburban Natural Gas Co. (Slip Opinion)
2021 Ohio 3224
Ohio
2021
Read the full case

Background

  • Suburban Natural Gas built a 4.9‑mile pipeline extension (placed in service Feb. 22, 2019) after engineering models showed pressure could fall below safe minimums during peak cold weather.
  • Suburban kept the project under five miles to use an expedited siting process; construction cost basis for rates was about $8.9 million.
  • Suburban applied to the PUCO for a rate increase; PUCO set the "date certain" for the used‑and‑useful inquiry as Feb. 28, 2019.
  • The Office of the Ohio Consumers’ Counsel (OCC) intervened and argued only about 2 miles were used and useful as of the date certain; PUCO staff and Suburban settled on inclusion of the full 4.9 miles.
  • PUCO approved recovery for the full 4.9 miles, citing engineering modeling and cost‑effectiveness (avoiding repeated small builds); OCC appealed.
  • The Ohio Supreme Court reversed and remanded, holding PUCO improperly relied on a prudence/prudent‑investment rationale rather than applying the statutory used‑and‑useful test as of the date certain.

Issues

Issue Plaintiff's Argument (OCC) Defendant's Argument (PUCO/Suburban) Held
Whether the remaining 2.9 miles of the 4.9‑mile extension were "used and useful" as of the date certain Only ~2 miles were useful on Feb. 28, 2019; the rest was overbuild and not compensable The full 4.9 miles were used and useful based on modeling and to avoid future incremental construction/regulatory costs Reversed and remanded: PUCO must determine used‑and‑useful status as of the date certain without importing future prudence reasoning
Whether PUCO permissibly relied on the prudence/prudent‑investment rationale when valuing plant Prudence is not the statutory standard for R.C. 4909.15(A)(1); only date‑certain usefulness matters Considering prudence and cost‑effectiveness is reasonable and consistent with regulatory practice to avoid inefficient re‑builds Error: PUCO applied the prudent‑investment test in lieu of the used‑and‑useful date‑certain inquiry; that was beyond its statutory mandate
Whether OCC was aggrieved by PUCO's approved three‑year phase‑in of the rate increase Phase‑in violates requirement to value property as of the date certain and could harm some customers Phase‑in benefits consumers and does not change the aggregate recovery; any harm speculative Court: OCC failed to show concrete aggrievement; challenge to phase‑in not sustained

Key Cases Cited

  • Smyth v. Ames, 169 U.S. 466 (U.S. 1898) (origin of the fair‑value/used‑and‑useful ratemaking concept)
  • Fed. Power Comm. v. Hope Natural Gas Co., 320 U.S. 591 (U.S. 1944) (rate‑making must result in just and reasonable rates; Supreme Court moved away from strict used‑and‑useful constitutional mandate)
  • Duquesne Light Co. v. Barasch, 488 U.S. 299 (U.S. 1989) (confirming Hope's just‑and‑reasonable standard)
  • Cincinnati v. Pub. Util. Comm., 113 Ohio St. 259 (Ohio 1925) (used‑and‑useful phrasing: property must be "actually used and useful for the convenience of the public")
  • Office of Consumers' Counsel v. Pub. Util. Comm., 58 Ohio St.2d 449 (Ohio 1979) (utility cannot recover for property not actually used and useful as of the date certain)
  • Office of Consumers' Counsel v. Pub. Util. Comm., 67 Ohio St.2d 153 (Ohio 1981) (usefulness must be measured as of the date certain; commission may not include unfinished or ineligible projects)
  • In re Application of Duke Energy Ohio, Inc., 82 N.E.3d 1148 (Ohio 2017) (statutory ratemaking framework, including rate‑base valuation, discussed)
  • Ohio Edison Co. v. Pub. Util. Comm., 63 Ohio St.3d 555 (Ohio 1992) (date certain tied to application timing; utility bears burden to prove proposals are just and reasonable)
Read the full case

Case Details

Case Name: In re Application of Suburban Natural Gas Co. (Slip Opinion)
Court Name: Ohio Supreme Court
Date Published: Sep 21, 2021
Citation: 2021 Ohio 3224
Docket Number: 2020-0781
Court Abbreviation: Ohio