midpage
Projects
Sign in to see your projects.
2018 Ohio 4697
Ohio
2018
Read the full case

Background

  • Ohio Power Company sought approval of its third electric-security plan (ESP) under R.C. 4928.143; the Public Utilities Commission of Ohio (PUCO) approved the ESP on Feb. 25, 2015.
  • The ESP included a Power Purchase Agreement (PPA) Rider tied to Ohio Power’s contract with OVEC; the rider was intended to act as a hedge and could operate as a surcharge or credit depending on PJM market revenues.
  • PUCO approved the PPA Rider only as a placeholder with the rate set at zero and required a separate proceeding for any cost recovery.
  • OCC and OMAEG sought rehearing and appealed the ESP Order challenging the zero-rate placeholder PPA Rider; Ohio Power later sought and obtained cost recovery through a separate PPA Rider proceeding (subject to a different appeal).
  • The Supreme Court sua sponte requested supplemental briefs on whether the ESP appeal should be dismissed for lack of prejudice and ultimately considered whether appellants showed harm from the ESP Order.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether appellants showed prejudice or harm from PUCO’s approval of the zero-rate placeholder PPA Rider in the ESP Order OCC/OMAEG: Approval without evaluating PPA Rider costs/benefits made ESP unlawful and harmed ratepayers; placeholder precluded effective challenge and was a prelude to rate increases PUCO/Ohio Power: Placeholder rider set at zero caused no present cost recovery or harm; any costs/benefits were unknown and were later reviewed in the PPA Rider proceeding curing any potential defect Court: Appellants failed to demonstrate actual or prejudicial harm from the ESP Order; appeal dismissed
Whether PUCO was required to quantify PPA Rider impacts in the ESP case under R.C. 4928.143(C)(1) OCC: PUCO unlawfully failed to analyze rider’s costs/benefits when approving ESP PUCO: Quantification was not feasible because the rider was a zero-rate placeholder; the statutory test was later applied when cost recovery was sought Court: PUCO’s conduct was permissible; absent evidence that inclusion of the PPA Rider would have rendered ESP less favorable, no reversible error shown
Whether future or imminent harm warrants addressing the ESP appeal despite lack of present harm OCC/OMAEG: Placeholder rider posed imminent risk of rate increases and irreparable harm PUCO: Future harms are addressed in the separate PPA Rider appeal where cost recovery was granted Court: Declined to resolve speculative future-harm allegations here; such claims can be pursued in the PPA Rider appeal
Whether regulatory delay in issuing a final ESP order caused compensable harm OMAEG: Delay in ruling prejudiced ratepayers and appellate rights PUCO: Delay was explained (federal uncertainty, litigation) and did not cause monetary injury because placeholder rider recovered no costs Court: OMAEG failed to show actual monetary injury or that delay was unreasonable; claim rejected

Key Cases Cited

  • Holladay Corp. v. Pub. Util. Comm., 61 Ohio St.2d 335 (Ohio 1980) (party seeking reversal of PUCO order must show prejudice or harm)
  • Constellation NewEnergy, Inc. v. Pub. Util. Comm., 104 Ohio St.3d 530 (Ohio 2004) (standard for reversing PUCO orders under R.C. 4903.13)
  • Monongahela Power Co. v. Pub. Util. Comm., 104 Ohio St.3d 571 (Ohio 2004) (appellate review of PUCO factual findings; manifest-weight standard)
  • MCI Telecommunications Corp. v. Pub. Util. Comm., 38 Ohio St.3d 266 (Ohio 1988) (questions of law reviewed de novo)
  • AK Steel Corp. v. Pub. Util. Comm., 95 Ohio St.3d 81 (Ohio 2002) (reaffirming burden to demonstrate prejudice when appealing PUCO orders)
Read the full case

Case Details

Case Name: In re Application of Ohio Power Co. (Slip Opinion)
Court Name: Ohio Supreme Court
Date Published: Nov 27, 2018
Citations: 2018 Ohio 4697; 155 Ohio St. 3d 320; 121 N.E.3d 315; 2017-0749
Docket Number: 2017-0749
Court Abbreviation: Ohio
Log In