History
  • No items yet
midpage
221 A.3d 777
Vt.
2019
Read the full case

Background

  • Derby GLC Solar sought a CPG to build a 500 kW group net-metered solar facility in Derby (VEC territory); PUC rescinded conditional waivers and held an evidentiary hearing.
  • Project site lies within the Sheffield‑Highgate Export Interface (SHEI), an export‑constrained area where ISO‑NE curtails local generation and lowers market prices.
  • Net‑metered output would act as a load reducer and, during export constraints, would increase curtailments of larger generators (notably GMP’s Kingdom Community Wind).
  • PUC found the project would cause additional curtailments, increasing ratepayer costs (PUC credited VEC’s ~$250,000 life‑of‑project estimate) and exacerbating SHEI congestion; no transmission upgrades exist to eliminate constraints.
  • PUC concluded the project failed 30 V.S.A. § 248(b)(10) (cannot be served economically without undue adverse effect) and (b)(7) (not consistent with Comprehensive Energy Plan) and denied the CPG; Derby appealed.

Issues

Issue Applicant's Argument State/Utilities' Argument Held
Whether PUC violated 3 V.S.A. § 812(a) / improperly refused to weigh project’s overall economic benefits (§ 248(b)(4)) PUC failed to rule on proposed economic‑benefit findings and should have balanced benefits (jobs, taxes) against harms § 248(b) has discrete criteria; PUC may decline to address (b)(4) once other § 248(b) criteria fail Affirmed: PUC need not decide (b)(4) once (b)(7) and (b)(10) fail; § 812 requirement satisfied by explanation given.
Whether PUC improperly relied on GMP expert testimony not in prefiled testimony PUC relied on late testimony estimating ‘‘several million dollars’’ impact without prior disclosure Practice rules permit oral examination; PUC did not base decision on that figure and error (if any) was harmless Affirmed: testimony permissible; no prejudicial error shown.
Whether PUC misinterpreted § 248(b)(10) by treating any adverse economic impact as “undue” Applicant: modest increased costs (~$250k) are not undue when weighed against project benefits PUC: in context of SHEI, displacement of cheaper existing renewables with no comparative benefits makes additional costs excessive/undue Affirmed: PUC’s application of “undue” is reasonable; adverse impacts here were excessive given no offsetting benefits.
Whether PUC misapplied § 248(b)(7), applied precedent inconsistently, or shifted burden Applicant: PUC treated similar past projects differently and forced applicant to disprove impacts State: changed ISO‑NE rules and new facts justify different outcome; applicant retained burden and PUC properly weighed evidence Affirmed: applicant failed to show inconsistent treatment; PUC permissibly considered changed circumstances and did not shift burden.

Key Cases Cited

  • Auclair v. Vermont Elec. Power Co., 329 A.2d 641 (Vt. 1974) (PUC action is a legislative, policy‑making process; PUC weighs alternatives).
  • UPC Vt. Wind, LLC, 969 A.2d 144 (Vt. 2009) (deference to PUC’s exercise of discretion and evidence‑weighing in § 248 proceedings).
  • In re New Haven GLC Solar, LLC, 175 A.3d 1211 (Vt. 2017) (appellate review limits and deference to PUC on CPG decisions).
  • In re Stowe Cady Hill Solar, LLC, 182 A.3d 53 (Vt. 2018) (PUC findings reviewed for clear error).
  • Vermont Elec. Power Co. v. Bandel, 375 A.2d 975 (Vt. 1977) (interpretation of “unduly” and legislative delegation to utility regulator).
  • In re Green Mountain Power Corp., 198 A.3d 36 (Vt. 2018) (distinguishing roles of § 248(b)(4) from other § 248 criteria).
  • In re Green Mountain Power Corp., 60 A.3d 654 (Vt. 2012) (PUC may consider testimony given at hearing even if it differs from prefiled testimony).
  • Sec’y, Agency of Natural Res. v. Upper Valley Reg’l Landfill Corp., 705 A.2d 1001 (Vt. 1997) (contested‑case requirement to rule on proposed findings).
  • In re Vermont Gas Sys., Inc., 187 A.3d 1138 (Vt. 2018) (distinguishing ratemaking proceedings where imprudence may be relevant).
Read the full case

Case Details

Case Name: In re Application of Derby GLC Solar, LLC
Court Name: Supreme Court of Vermont
Date Published: Oct 18, 2019
Citations: 221 A.3d 777; 2019 VT 77; 2019-078
Docket Number: 2019-078
Court Abbreviation: Vt.
Log In
    In re Application of Derby GLC Solar, LLC, 221 A.3d 777