History
  • No items yet
midpage
In re Application of Columbus S. Power Co.
8 N.E.3d 863
Ohio
2014
Read the full case

Background

  • AEP filed an electric security plan (ESP) for 2009–2011 under R.C. 4928.143; PUCO originally approved it in 2009. Appellants Ohio Consumers’ Counsel (OCC) and Industrial Energy Users‑Ohio (IEU) appealed.
  • This court’s 2011 decision (Columbus S. Power) reversed PUCO on three grounds: a retroactive rate increase, improper recovery authority for environmental-investment carrying costs, and an unsupported POLR (provider‑of‑last‑resort) charge; the case was remanded to PUCO for further consideration of carrying costs and POLR issues.
  • On remand PUCO concluded carrying costs were authorized under R.C. 4928.143(B)(2)(d), and therefore no refund of those amounts collected during remand was required. PUCO found AEP had not proven actual POLR costs and ordered removal of the POLR charge from tariffs and refund of POLR amounts collected during the remand period (June–Oct 2011).
  • OCC and IEU sought broader refunds: (1) repayment or offset of POLR and carrying charges AEP collected from April 2009–May 2011; and (2) related adjustments to deferred fuel-cost balances and other ratemaking components (delta revenues, USF, SEET).
  • PUCO denied those broader remedies; the commission explained refunds or offsets of previously collected charges would constitute retroactive ratemaking, barred by precedent and statute. This appeal followed; the Supreme Court affirms PUCO.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether environmental‑investment carrying costs are recoverable under R.C. 4928.143(B)(2)(d) IEU: statute requires a showing that charges are "necessary" (or economically justified) to provide "certainty" PUCO/AEP: statute requires only that charges have the effect of stabilizing or providing certainty regarding retail service; no necessity or separate economic‑need showing required Court: Affirmed PUCO — (B)(2)(d) authorizes carrying charges; record supported finding that carrying costs provided price stability/certainty for generation service
Whether recovery of carrying costs during remand was unlawful IEU: PUCO improperly allowed collection during remand after the court’s prior decision PUCO: May allow collection subject to refund; IEU waived challenge by not timely contesting PUCO’s interim order Court: IEU waived challenge to PUCO’s May 25, 2011 order due to delay; claim forfeited
Whether AEP must refund or offset POLR charges collected Apr 2009–May 2011 against deferred fuel costs OCC/IEU: POLR collections were unlawful and must be refunded or deducted from deferred FAC balance PUCO/AEP: Rates were valid while in effect; refund/offset would be retroactive ratemaking; appellants could have sought a stay under R.C. 4903.16 during appeal Court: Affirmed PUCO — retroactive ratemaking bar (Keco and subsequent precedent) precludes refund or offset; appellants failed to seek stay so cannot recover those amounts
Whether PUCO must adjust delta revenues, USF, SEET because POLR was unlawfully collected IEU: POLR is embedded in those calculations and overstates revenues/earnings; adjustments required PUCO/AEP: POLR was not treated as unlawful for period in question; retroactive adjustments barred Court: Dismissed — based on holding that POLR collections need not be disgorged, these derivative adjustment claims fail

Key Cases Cited

  • Keco Indus., Inc. v. Cincinnati & Suburban Bell Tel. Co., 166 Ohio St. 254 (1957) (no right to restitution for rate increases collected during pendency of appeal; bar to retroactive ratemaking absent statutory authority)
  • In re Application of Columbus S. Power Co., 128 Ohio St.3d 512 (2011) (Supreme Court previously reversed PUCO on retroactive increase, carrying‑costs authority, and POLR methodology; remanded for further proceedings)
  • Constellation NewEnergy, Inc. v. Pub. Util. Comm., 104 Ohio St.3d 530 (2004) (explains POLR concept and PUCO ratemaking standards)
  • Lucas Cty. Commrs. v. Pub. Util. Comm., 80 Ohio St.3d 344 (1997) (utility ratemaking is prospective only; courts and PUCO cannot order refunds of previously approved rates)
  • Cleveland Elec. Illum. Co. v. Pub. Util. Comm., 46 Ohio St.2d 105 (1976) (a remand does not automatically render existing rates unlawful; commission must implement court mandate by new order)
Read the full case

Case Details

Case Name: In re Application of Columbus S. Power Co.
Court Name: Ohio Supreme Court
Date Published: Feb 13, 2014
Citation: 8 N.E.3d 863
Docket Number: 2012-0187
Court Abbreviation: Ohio