History
  • No items yet
midpage
In re Application of Buckeye Wind, L.L.C.
131 Ohio St. 3d 449
| Ohio | 2012
Read the full case

Background

  • Buckeye Wind proposed a 70-turbine wind farm in Champaign County, Ohio exceeding 126 MW, requiring Power Siting Board (PSB) approval as a major utility facility.
  • Buckeye filed a 1,500-page application for environmental compatibility and public need in April 2009; neighbors UNU et al. and Champaign County/intervenors opposed.
  • Board granted construction certificate with 70 conditions; neighbors sought more protection and challenged bond sufficiency.
  • County sought bonding to cover road damages and turbine decommissioning; the board set a $5,000 bond for the first year.
  • The court reviewed PSB’s decision under R.C. 4906, affirming the certificate as issued with mitigation conditions; dissenters challenged delegation to staff and procedural public participation.
  • The majority held that the process complied with statutes, that staff condition recommendations were properly tied to certificate conditions, and that no remand was necessary.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the board properly conducted hearings and public input Neighbors argue rights to call witnesses and full hearing were violated Board and Buckeye contend intervenors participated and hearings complied with rules No reversible error; hearings and public input were adequate.
Whether the board improperly delegated decisionmaking to staff Delegation undermines board's ultimate responsibility Statutes allow staff to monitor compliance under conditions; board retains final authority Not improper delegation; board retains control and can modify certificate through conditions.
Whether the certificate should be issued before all issues are finally resolved Issues must be fully resolved by board before granting certificate R.C. 4906.10 allows issuance with conditions and ongoing review Certificate issued with 70 conditions; no need for further immediate hearing.
Whether bonding for decommissioning is adequate Bond ($5,000 per turbine) is inadequate to ensure decommissioning Bond amount supported by testimony and context; decommissioning risks addressed by conditions Bond adequacy upheld; no remand required.
Whether noise setbacks and environmental impacts are reasonable Neighbors claim noise limits/setbacks are vague or too lenient Board’s flexible, case-by-case approach is permissible given evolving technology Noise/setbacks are supported; board properly balanced technology and impacts.

Key Cases Cited

  • In re Application of Am. Transm. Sys., Inc., 125 Ohio St.3d 333 (2010-Ohio-1841) (delegation allowed but board must retain decisionmaking authority)
  • Chester Twp. v. Power Siting Comm., 49 Ohio St.2d 231 (1977) (standard of review for PSB orders)
  • Ohio Consumers' Counsel v. Pub. Util. Comm., 121 Ohio St.3d 362 (2009-Ohio-604) (complete and independent power of review over board orders)
  • Constellation NewEnergy, Inc. v. Pub. Util. Comm., 104 Ohio St.3d 530 (2004-Ohio-6767) (unified standard of review for PSB orders)
Read the full case

Case Details

Case Name: In re Application of Buckeye Wind, L.L.C.
Court Name: Ohio Supreme Court
Date Published: Mar 6, 2012
Citation: 131 Ohio St. 3d 449
Docket Number: 2010-1554
Court Abbreviation: Ohio