History
  • No items yet
midpage
IAP Worldwide Services, Inc.
ASBCA No. 59397, 59398, 59399
A.S.B.C.A.
May 17, 2017
Read the full case

Background

  • IAP Worldwide held an IDIQ fixed-price contract with the U.S. Army Corps of Engineers to supply and install large generator plants at three Afghan forward operating bases (Shank, Dwyer, Sharana).
  • IAP based its proposals on shipping heavy equipment via the Pakistan route (UAE → Karachi → overland into Afghanistan); that route was normally fastest and least costly and had been used repeatedly.
  • On 28 Nov 2011 Pakistan closed its border and port to U.S./NATO shipments after a military incident; shipments already in Karachi were detained and other planned shipments were halted.
  • IAP timely notified the contracting officer of delay and requested schedule relief; the contracting officer initially refused extensions and warned of default, then later granted only 75 days for two of the task orders and none for the third.
  • Facing threats of default and insufficient extensions, IAP shipped equipment via the costlier, slower Northern Distribution Network (NDN) and leased/shipped a second set of generators for Shank, incurring substantial extra costs.
  • IAP submitted certified claims for increased costs; the Board found Pakistan’s closure was an excusable delay but that the government’s refusal/insufficient extensions amounted to constructive acceleration, entitling IAP to equitable adjustment for costs reasonably and actually incurred in complying with acceleration.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Constructive acceleration (claim for extra costs) Government denied timely/sufficient extensions after an excusable delay and threatened default, forcing IAP to incur extra costs to meet deadlines Government contends delay was physically/legally avoidable (NDN or air available) and later granted 75-day extensions Held for IAP: excusable delay admitted; initial refusals + inadequate 75-day extensions and default threats constituted constructive acceleration; IAP entitled to equitable adjustment for extra, reasonable costs incurred to comply
Constructive change (government-directed work) Government’s conduct in demanding timely performance effectively required IAP to use alternate, costlier routes—a constructive change Government says it did not order NDN shipments; contractor assumed transport risk under fixed-price contract Held for IAP as corollary to acceleration: government’s acceleration rendered it liable for resulting constructive change costs
Constructive suspension / government convenience IAP argues government’s handling caused a constructive suspension entitling it to costs Government says border closure was action by Pakistan, not government convenience Held for government: no constructive suspension—closure was a third-party act, not for government convenience
Warranty of route availability / breach IAP argues government implicitly warranted availability of Pakistan route via approvals/course of dealing Government relies on FAR clauses and fixed-price allocation of transport risk; no explicit warranty Held for government: no warranty established; risk of third-party closures not assumed by government

Key Cases Cited

  • Zafer Taahhut Insaat ve Ticaret A.S. v. United States, 833 F.3d 1356 (Fed. Cir. 2016) (defines elements of constructive acceleration)
  • Fraser Constr. Co. v. United States, 384 F.3d 1354 (Fed. Cir. 2004) (standard for acceleration recovery under changes clause)
  • Norair Eng'g Corp. v. United States, 666 F.2d 546 (Ct. Cl. 1981) (acceleration where government insists on original schedule despite excusable delay)
  • Jennie-O Foods, Inc. v. United States, 580 F.2d 400 (Ct. Cl. 1978) (discusses limits on extension entitlement when alternate performance methods exist)
  • Merritt-Chapman & Scott Corp. v. United States, 429 F.2d 431 (Ct. Cl. 1970) (constructive suspension for unreasonable government delay for its convenience)
  • Raytheon Co. v. White, 305 F.3d 1354 (Fed. Cir. 2002) (commercial impracticability and constructive change principles)
  • Oman-Fischbach Int'l (JV) v. Pirie, 276 F.3d 1380 (Fed. Cir. 2002) (elements for government breach of warranty)
Read the full case

Case Details

Case Name: IAP Worldwide Services, Inc.
Court Name: Armed Services Board of Contract Appeals
Date Published: May 17, 2017
Docket Number: ASBCA No. 59397, 59398, 59399
Court Abbreviation: A.S.B.C.A.