History
  • No items yet
midpage
75 F.4th 248
1st Cir.
2023
Read the full case

Background

  • GE contaminated the Housatonic River with PCBs; a 2000 Consent Decree required a RCRA corrective-action permit for remediation of the “Rest of River” (Reaches 5–16) and adoption of CERCLA/NCP cleanup standards and ARARs.
  • EPA issued a 2016 RCRA permit requiring extensive excavation upstream, capping, monitored natural recovery (MNR) downstream, no mandated treatment of excavated material, and fully offsite disposal of removed material; several parties appealed.
  • In 2018 the EAB largely upheld the 2016 permit but remanded the disposal decision, finding EPA had not adequately addressed whether an onsite facility could meet TSCA or waiver requirements.
  • After confidential mediation (Settlement) among EPA, GE, state and local stakeholders (not joined by the petitioners), EPA issued a 2020 draft and then a final permit adopting enhanced remediation, continued MNR downstream, no required large-scale treatment, and a hybrid disposal approach (onsite for lower‑contaminated material; offsite for higher‑contaminated material).
  • Petitioners (HRI and HEAL) challenged the 2020 permit on procedural grounds (mediation/settlement process) and substantively as to MNR, treatment requirements, and the hybrid disposal plan (including EPA’s waiver of a Massachusetts ACEC regulation).

Issues

Issue Petitioners' Argument EPA/Respondents' Argument Held
Procedural challenge to off‑record mediation/Settlement Mediation’s secrecy and covenants made notice-and-comment a façade and violated the Consent Decree, CERCLA, and APA Consent Decree permits confidential mediation; EPA provided full public comment on the draft permit and responded; no APA/CERCLA bar to pre-draft settlement Denied — mediation and Settlement were procedurally permissible; public comment occurred and EPA explained responses
Legality/adequacy of MNR downstream Insufficient baseline data, no sediment performance standard, no reasonable timeframe or contingency if MNR fails EPA relied on extensive sediment/fish data, adopted fish‑tissue and downstream transport performance standards with timeframes and contingency procedures Denied — EPA’s selection of MNR upheld as reasonable and consistent with Consent Decree/CERCLA/NCP
Requirement to mandate treatment (thermal desorption/bioremediation) EPA should have required treatment of excavated material and CERCLA’s treatment preference was not satisfied EPA studied treatment; thermal desorption and bioremediation impracticable/uncertain, costly, or ineffective; EPA provided published explanations and required alternative amendments (e.g., activated carbon) where appropriate Denied — EPA permissibly declined to require large‑scale treatment and complied with CERCLA’s preference-by-explanation framework
Hybrid disposal and ACEC waiver (change from 2016 offsite policy) Hybrid disposal was an unexplained reversal driven by settlement politics; siting onsite in an ACEC unlawful EPA reasoned change: new facts (less contaminated onsite average, cap/liner/leachate/monitoring), comparative weighing of the nine Selection Criteria (cost, transport/GHG, implementability, community support), and CERCLA waiver valid because offsite option posed greater overall risk Denied — EPA provided adequate reasoned explanation for hybrid approach, lawfully waived the ACEC ARAR, and record supplementation was rejected

Key Cases Cited

  • Perez v. Mortg. Bankers Ass'n, 575 U.S. 92 (2015) (courts may not impose extra APA procedures beyond statutory minima)
  • Vt. Yankee Nuclear Power Corp. v. Nat. Res. Def. Council, 435 U.S. 519 (1978) (agencies free to grant additional procedures but courts may not impose them)
  • FCC v. Fox Television Stations, Inc., 556 U.S. 502 (2009) (agency must acknowledge and reasonably explain a change in position)
  • Encino Motorcars, LLC v. Navarro, 579 U.S. 211 (2016) (reasoned explanation required for policy reversals, but not a heightened standard)
  • Motor Vehicle Mfrs. Ass'n v. State Farm, 463 U.S. 29 (1983) (arbitrary-and-capricious standard)
  • Friends of the Earth, Inc. v. Laidlaw Env't Servs., 528 U.S. 167 (2000) (environmental plaintiffs’ standing based on use and aesthetic harms)
  • United States v. Cannons Eng'g Corp., 899 F.2d 79 (1st Cir.) (1990) (CERCLA encourages prompt settlement)
  • City of Taunton v. EPA, 895 F.3d 120 (1st Cir. 2018) (deference to EPA technical decisions)
  • Upper Blackstone Water Pollution Abatement Dist. v. U.S. EPA, 690 F.3d 9 (1st Cir. 2012) (scope of review/deference to permitting decisions)
  • NLRB v. Lily Transp. Corp., 853 F.3d 31 (1st Cir. 2017) (treatment of agency position changes in light of new facts)
  • Town of Winthrop v. FAA, 535 F.3d 1 (1st Cir. 2008) (narrow exceptions for supplementing administrative record)
Read the full case

Case Details

Case Name: Housatonic River Initiative v. U.S. Environmental Protection Agency
Court Name: Court of Appeals for the First Circuit
Date Published: Jul 25, 2023
Citations: 75 F.4th 248; 22-1398
Docket Number: 22-1398
Court Abbreviation: 1st Cir.
Log In
    Housatonic River Initiative v. U.S. Environmental Protection Agency, 75 F.4th 248